BILL NUMBER: AB 396	INTRODUCED
	BILL TEXT


INTRODUCED BY   Assembly Member Fuentes

                        FEBRUARY 23, 2009

   An act to amend Sections 3186, 3252, 3260, 3260.1, and 3262.5 of,
and to add Section 3260.5 to, the Civil Code, and to amend Sections
7107, 10261, and 10261.5 of, and to add Section 7201 to, the Public
Contract Code, relating to works of improvement.


	LEGISLATIVE COUNSEL'S DIGEST


   AB 396, as introduced, Fuentes. Works of improvement: liens.
   (1) Existing law provides that all persons and laborers of every
class, except for an original contractor, performing labor upon,
bestowing skill or other necessary services on, furnishing materials
or leasing equipment to be used or consumed in, or furnishing
appliances, teams, or power contributing to, a public work of
improvement may serve a stop notice upon the public entity
responsible for the public work, as specified. Existing law imposes a
duty on a public entity to withhold money or bonds due or to become
due to the original contractor in an amount sufficient to answer the
claim stated in the stop notice and to provide for the public entity'
s reasonable cost of any litigation on the matter, as specified.
   This bill would qualify the requirement that the public entity
withhold money or bonds sufficient to provide for reasonable
litigation costs to make it applicable only if the original
contractor fails to promptly accept a tender of defense of the public
entity in the litigation.
   (2) Existing law requires that a 20-day public work preliminary
bond notice be given under specified circumstances. If the notice is
not given, a claimant may enforce a claim by giving written notice to
the surety and the bond principal within 15 days after recordation
of a notice of completion. If no notice of completion has been
recorded, the time for giving written notice to the surety and the
bond principal is extended to 75 days after completion of the work of
improvement.
   This bill would provide, instead, if no notice is given, a
claimant may enforce a claim by giving written notice to the surety
and the bond principal prior to the completion of the project or
recordation of a notice of completion.
   (3) Existing law imposes a penalty of 2% per month on funds that
are improperly withheld in a contract dispute relating to public and
private works of improvement, as specified. Existing law requires any
person or corporation that has contracted to do business with a
public utility to pay any subcontractor within 15 working days of
receipt of each progress payment from the public utility, except as
specified. Existing law also requires a state agency that fails to
make any progress payment within 30 days after receipt of the payment
request to pay interest at the rate of 10% per year.
   This bill would revise, recast, and consolidate these and various
other provisions governing the timely payment of progress payments,
retention proceeds, and final payments under a contract for a public
or private work of improvement with respect to contracts entered into
on or after January 1, 2010. The bill would make the 2% penalty
described above, in lieu of any interest otherwise due, applicable to
an owner, including a public utility or a state agency, a
contractor, or a subcontractor that fails to make timely progress,
retention, or final payments, as specified. The bill would revise and
recast notice and withholding requirements in the case of a dispute,
as specified.
   (4) Existing law provides that in a contract between the original
contractor and a subcontractor, and in a contract between a
subcontractor and any subcontractor thereunder, the percentage of
retention proceeds withheld cannot exceed the percentage specified in
the contract between the public entity and the original contractor.
   This bill would instead require that retention proceeds not exceed
5% of the payment, as specified, for all contracts entered into on
or after January 1, 2010, between a public entity, as defined, and an
original contractor, between an original contractor and a
subcontractor, and between all subcontractors thereunder.
   (5) Existing law requires the Department of General Services to
withhold not less than 5% of the contract price for a public work of
improvement until final completion and acceptance of the project.
   This bill would require the Department of General Services to
withhold not more than 5% of the contract price until final
completion and acceptance of the project.
   Vote: majority. Appropriation: no. Fiscal committee: yes.
State-mandated local program: no.


THE PEOPLE OF THE STATE OF CALIFORNIA DO ENACT AS FOLLOWS:

  SECTION 1.  Section 3186 of the Civil Code is amended to read:
   3186.  It shall be the duty of the public entity, upon receipt of
a stop notice pursuant to this chapter, to withhold from the original
contractor, or from any person acting under his or her authority,
money or bonds  (where   , if  bonds are to
be issued in payment for the work of  improvement) 
 improvement, that are  due or to become due to that
contractor in an amount sufficient to  (a)  answer the claim
stated in the stop notice and  to   (b) 
provide for the public entity's reasonable cost of any litigation
thereunder  , if the original contractor fails to promptly accept
a tender of defense of the public entity in the litigation  .
The public entity may satisfy this duty by refusing to release money
held in escrow pursuant to Section 10263 or 22300 of the Public
Contract Code.
  SEC. 2.  Section 3252 of the Civil Code is amended to read:
   3252.  (a) With regard to a contract entered into on or after
January 1, 1995, in order to enforce a claim upon any payment bond
given in connection with a public work, a claimant shall give the
20-day public works preliminary bond notice as provided in Section
3098.
   (b) If the 20-day public work preliminary bond notice was not
given as provided in Section 3098, a claimant may enforce a claim by
giving written notice to the surety and the bond principal as
provided in Section 3227  within 15 days after recordation of
a notice of completion. If no notice of completion has been
recorded, the time for giving written notice to the surety and the
bond principal is extended to 75 days after completion of the work of
improvement   prior to the completion of the project,
as defined in Section 3086, or recordation of a notice of completion
 .
  SEC. 3.  Section 3260 of the Civil Code is amended to read:
   3260.  (a) This section is applicable with respect to all
contracts entered into on or after July 1, 1991, relating to the
construction of any private work of improvement. However, the
amendments made to this section during the 1992 portion of the
1991-92 Regular Session of the Legislature are applicable only with
respect to contracts entered into on or after January 1, 1993,
relating to the construction of any private work of improvement.
Moreover, the amendments made to this section during the 1993 portion
of the 1993-94 Regular Session of the Legislature are applicable
only with respect to contracts entered into on or after January 1,
1994, relating to the construction of any private work of
improvement. 
   (b) This section shall apply only to contracts entered into prior
to January 1, 2010.  
   (b) 
    (c)  The retention proceeds withheld from any payment by
the owner from the original contractor, or by the original
contractor from any subcontractor, shall be subject to this section.

   (c) 
    (d)  Within 45 days after the date of completion, the
retention withheld by the owner shall be released. "Date of
completion," for purposes of this section, means any of the
following:
   (1) The date of issuance of any certificate of occupancy covering
the work by the public agency issuing the building permit.
   (2) The date of completion indicated on a valid notice of
completion recorded pursuant to Section 3093.
   (3) The date of completion as defined in Section 3086.
   However, release of retentions withheld for any portion of the
work of improvement which ultimately will become the property of a
public agency, may be conditioned upon the acceptance of the work by
the public agency. In the event of a dispute between the owner and
the original contractor, the owner may withhold from the final
payment an amount not to exceed 150 percent of the disputed amount.

   (d) 
    (e)  Subject to subdivision  (e)  
(f) , within 10 days from the time that all or any portion of
the retention proceeds are received by the original contractor, the
original contractor shall pay each of its subcontractors from whom
retention has been withheld, each subcontractor's share of the
retention received. However, if a retention payment received by the
original contractor is specifically designated for a particular
subcontractor, payment of the retention shall be made to the
designated subcontractor, if the payment is consistent with the terms
of the subcontract. 
   (e) 
    (f)  If a bona fide dispute exists between a
subcontractor and the original contractor, the original contractor
may withhold from that subcontractor with whom the dispute exists its
portion of the retention proceeds. The amount withheld from the
retention payment shall not exceed 150 percent of the estimated value
of the disputed amount. 
   (f) 
    (g)  Within 10 days of receipt of written notice by the
owner from the original contractor or by the original contractor from
the subcontractor, as the case may be, that any work in dispute has
been completed in accordance with the terms of the contract, the
owner or original contractor shall advise the notifying party of the
acceptance or rejection of the disputed work. Within 10 days of
acceptance of the disputed work, the owner or original contractor, as
the case may be, shall release the retained portion of the retention
proceeds. 
   (g) 
    (h)  In the event that retention payments are not made
within the time periods required by this section, the owner or
original contractor withholding the unpaid amounts shall be subject
to a charge of 2 percent per month on the improperly withheld amount,
in lieu of any interest otherwise due. Additionally, in any action
for the collection of funds wrongfully withheld, the prevailing party
shall be entitled to his or her attorney's fees and costs. 
   (h) 
    (i)  It shall be against public policy for any party to
require any other party to waive any provision of this section.

   (i) 
    (j)  This section shall not be construed to apply to
retentions withheld by a lender in accordance with the construction
loan agreement.
  SEC. 4.  Section 3260.1 of the Civil Code is amended to read:
   3260.1.  (a) This section is applicable with respect to all
contracts entered into on or after January 1, 1992, relating to the
construction of any private work of improvement. 
   (b) This section shall apply only to contracts entered into prior
to January 1, 2010.  
   (b) 
    (c)  Except as otherwise agreed in writing, the owner
shall pay to the contractor, within 30 days following receipt of a
demand for payment in accordance with the contract, any progress
payment due thereunder as to which there is no good faith dispute
between the parties. In the event of a dispute between the owner and
the contractor, the owner may withhold from the progress payment an
amount not to exceed 150 percent of the disputed amount. If any
amount is wrongfully withheld in violation of this subdivision, the
contractor shall be entitled to the penalty specified in subdivision
 (g)   (h)  of Section 3260. 
   (c) 
    (d)  Nothing in this section shall be deemed to
supersede any requirement of Section 3260 respecting the withholding
of retention proceeds.
  SEC. 5.  Section 3260.5 is added to the Civil Code, to read:
   3260.5.  (a) Notwithstanding any other law, this section applies
to all contracts entered into on or after January 1, 2010, relating
to the construction of any private or public work of improvement.
   (b) This section applies to contractual obligations between all of
the following entities:
   (1) Owners and original contractors.
   (2) Original contractors and subcontractors.
   (3) Subcontractors and subcontractors.
   (c) The owner shall pay to the contractor, within 30 days
following receipt of a demand for payment, any progress payment due
if there is no good faith dispute between the parties.
   (d) (1) Within 45 days after the date of completion, or 100 days
after cessation of labor, the retention proceeds or final payment
withheld by the owner shall be released. "Date of completion," for
purposes of this section, means any of the following:
   (A) The date of issuance of any certificate of occupancy covering
the work by the public agency issuing the building permit.
   (B) The date of completion indicated on a valid notice of
completion recorded pursuant to Section 3093.
   (C) The date of completion as defined in Section 3086.
   (2) Notwithstanding paragraph (1), the release of retention
proceeds or final payments, withheld for any portion of a work of
improvement which ultimately will become the property of a public
agency, may be conditioned upon the acceptance of the work by the
public agency.
   (e) Subject to subdivision (h), within 10 days from the time that
all or any portion of the progress payment, retention proceeds, or
final payment is received by the original contractor, the original
contractor shall pay each of its subcontractors from which the
progress payment, retention proceeds, or final payment has been
withheld, each subcontractor's share of the progress payment,
retention proceeds, or final payment received. However, if the
progress payment, retention proceeds, or final payment received by
the original contractor is specifically designated for a particular
subcontractor, payment of the progress payment, retention proceeds,
or final payment shall be made to the designated subcontractor.
   (f) If a bona fide dispute exists between an owner and original
contractor or between the original contractor and a subcontractor,
the owner or original contractor may withhold from the party with
which the dispute exists an amount not to exceed 150 percent of the
disputed amount. The amount withheld shall not exceed 150 percent of
the estimated value of the disputed amount.
   (g) Within 10 days of receipt of written notice by the owner form
the original contractor, or by the original contractor from the
subcontractor, that any work in dispute has been completed in
accordance with the terms of the contract, the owner or original
contractor shall advise the notifying party of the acceptance or
rejection of the disputed work. Within 10 days of acceptance of the
disputed work, the owner or original contractor shall release the
retained portion of the disputed payment.
   (h) If any payment is not made within the time periods required by
this section, the owner or original contractor withholding the
unpaid amount shall be subject to a charge of 2 percent per month on
the improperly withheld amount, in lieu of any interest otherwise
due. Additionally, in any action for the collection of funds
wrongfully withheld, the prevailing party shall be entitled to
attorney's fees and costs.
   (i) It is against public policy for any party to require any other
party to waive any provision of this section.
   (j) The remedies authorized pursuant to this section are separate
from, and in addition to, any other remedy authorized by law.
  SEC. 6.  Section 3262.5 of the Civil Code is amended to read:
   3262.5.  (a)  This section shall apply only to contracts
entered into prior to January 1, 2010. 
    (b)  Any person or corporation which has contracted to
do business with a public utility, hereafter referred to in this
section as a contractor, shall pay any subcontractors within 15
working days of receipt of each progress payment from the public
utility, unless otherwise agreed in writing by the parties, the
respective amounts allowed the contractor on account of the work
performed by the subcontractors, to the extent of each of the
subcontractors' interest in that work. In the event that there is a
good faith dispute over all or any portion of the amount due on a
progress payment from a contractor to a subcontractor, then the
contractor may withhold no more than 150 percent of the disputed
amount. 
   (b) 
    (c)  Any contractor who violates this section shall pay
to the subcontractor a penalty of 2 percent of the disputed amount
due per month for every month that payment is not made. In any action
for the collection of funds wrongfully withheld, the prevailing
party shall be entitled to his or her attorney's fees and costs.

   (c) 
    (d)  This section shall not be construed to limit or
impair any contractual, administrative, or judicial remedies
otherwise available to a contractor or a subcontractor in the event
of a dispute involving late payment or nonpayment by a contractor, or
deficient performance or nonperformance by a subcontractor.
  SEC. 7.  Section 7107 of the Public Contract Code is amended to
read:
   7107.  (a) This section is applicable with respect to all
contracts entered into on or after January 1, 1993, relating to the
construction of any public work of improvement. 
   (b) This section shall apply only to contracts entered into prior
to January 1, 2010.  
   (b) 
    (c)  The retention proceeds withheld from any payment by
the public entity from the original contractor, or by the original
contractor from any subcontractor, shall be subject to this section.

   (c) 
    (d)  Within 60 days after the date of completion of the
work of improvement, the retention withheld by the public entity
shall be released. In the event of a dispute between the public
entity and the original contractor, the public entity may withhold
from the final payment an amount not to exceed 150 percent of the
disputed amount. For purposes of this subdivision, "completion" means
any of the following:
   (1) The occupation, beneficial use, and enjoyment of a work of
improvement, excluding any operation only for testing, startup, or
commissioning, by the public agency, or its agent, accompanied by
cessation of labor on the work of improvement.
   (2) The acceptance by the public agency, or its agent, of the work
of improvement.
   (3) After the commencement of a work of improvement, a cessation
of labor on the work of improvement for a continuous period of 100
days or more, due to factors beyond the control of the contractor.
   (4) After the commencement of a work of improvement, a cessation
of labor on the work of improvement for a continuous period of 30
days or more, if the public agency files for record a notice of
cessation or a notice of completion. 
   (d) 
    (e)  Subject to subdivision  (e)  
(f)  , within seven days from the time that all or any portion
of the retention proceeds are received by the original contractor,
the original contractor shall pay each of its subcontractors from
whom retention has been withheld, each subcontractor's share of the
retention received. However, if a retention payment received by the
original contractor is specifically designated for a particular
subcontractor, payment of the retention shall be made to the
designated subcontractor, if the payment is consistent with the terms
of the subcontract. 
   (e) 
    (f)  The original contractor may withhold from a
subcontractor its portion of the retention proceeds if a bona fide
dispute exists between the subcontractor and the original contractor.
The amount withheld from the retention payment shall not exceed 150
percent of the estimated value of the disputed amount. 
   (f) 
    (g)  In the event that retention payments are not made
within the time periods required by this section, the public entity
or original contractor withholding the unpaid amounts shall be
subject to a charge of 2 percent per month on the improperly withheld
amount, in lieu of any interest otherwise due. Additionally, in any
action for the collection of funds wrongfully withheld, the
prevailing party shall be entitled to attorney's fees and costs.

   (g) 
    (h)  If a state agency retains an amount greater than
125 percent of the estimated value of the work yet to be completed
pursuant to Section 10261, the state agency shall distribute
undisputed retention proceeds in accordance with subdivision 
(c)   (d)  . However, notwithstanding subdivision
 (c)   (d)  , if a state agency retains an
amount equal to or less than 125 percent of the estimated value of
the work yet to be completed, the state agency shall have 90 days in
which to release undisputed retentions. 
   (h) 
    (i)  Any attempted waiver of the provisions of this
section shall be void as against the public policy of this state.
  SEC. 8.  Section 7201 is added to the Public Contract Code, to
read:
   7201.  (a) (1) This section shall apply with respect to all
contracts entered into on or after January 1, 2010, between a public
entity and an original contractor, between an original contractor and
a subcontractor, and between all subcontractors thereunder, relating
to the construction of any public work of improvement.
   (2) Under no circumstances shall any provision of this section be
construed to limit the ability of any public entity to withhold 150
percent of the value of any disputed amount of work from the final
payment, as provided for in subdivision (c) of Section 7107. In the
event of a good faith dispute, nothing in this section shall be
construed to require a public entity to pay for work that is not
approved or accepted in accordance with the proper plans or
specifications.
   (3) For purposes of this section, "public entity" means the state,
including every state agency, office, department, division, bureau,
board, or commission, the California State University, the University
of California, a city, county, city and county, including chartered
cities and chartered counties, district, special district, public
authority, political subdivision, public corporation, or nonprofit
transit corporation wholly owned by a public agency and formed to
carry out the purposes of the public agency.
   (b) (1) The retention proceeds withheld from any payment by a
public entity from the original contractor, by the original
contractor from any subcontractor, and by a subcontractor from any
subcontractor thereunder shall not exceed 5 percent of the payment.
In no event shall the total retention proceeds withheld exceed 5
percent of the contract price. In a contract between the original
contractor and a subcontractor, and in a contract between a
subcontractor and any subcontractor thereunder, the percentage of the
retention proceeds withheld may not exceed the percentage specified
in the contract between the public entity and the original
contractor.
   (2) This subdivision shall not apply if the contractor provides
written notice to the subcontractor, prior to or at the time that the
bid is requested, that a bond may be required and the subcontractor
subsequently is unable or refuses to furnish to the contractor a
performance or payment bond issued by an admitted surety insurer.
   (c) No party identified in subdivision (a) may require any other
party to waive any provision of this section.
  SEC. 9.  Section 10261 of the Public Contract Code is amended to
read:
   10261.  Payments upon contracts shall be made as the department
prescribes upon estimates made and approved by the department, but
progress payments shall not be made in excess of 95 percent of the
percentage of actual work completed plus a like percentage of the
value of material delivered on the ground or stored subject to or
under the control of the state, and unused, except as otherwise
provided in this section. The department shall withhold not 
less   more  than 5 percent of the contract price
until final completion and acceptance of the project. However, at any
time after 95 percent of the work has been completed, the department
may reduce the funds withheld to an amount not less than 125 percent
of the estimated value of the work yet to be completed, as
determined by the department, if the reduction has been approved, in
writing, by the surety on the performance bond and by the surety on
the payment bond. The Controller shall draw his or her warrants upon
estimates so made and approved by the department and the Treasurer
shall pay them. The funds may be released by electronic transfer if
that procedure is requested by the contractor, in writing, and if the
public entity has, in place at the time of the request, the
mechanism for the transfer.
  SEC. 10.  Section 10261.5 of the Public Contract Code is amended to
read:
   10261.5.  (a)  This section shall apply only to contracts
entered into prior to January 1, 2010. 
    (b)  Any state agency which fails to make any progress
payment within 30 days after receipt of the payment request from a
contractor on a construction contract for an undisputed payment
request, which was properly submitted by the contractor to the
agency, shall pay interest to the contractor equivalent to the legal
rate set forth in subdivision (a) of Section 685.010 of the Code of
Civil Procedure. Any state agency which independently calculates the
amount due on a progress payment and which fails to make a progress
payment within 30 days of the first submittal of the estimate for
each contract by the engineer, shall pay interest to the contractor
equivalent to the legal rate set forth in subdivision (a) of Section
685.010 of the Code of Civil Procedure. In the event that the payment
is not made within 30 days of receipt of the contractor's request or
the first submittal by the engineer, and the Controller has
processed the payment within 14 days of receipt of the request or
submittal, the contracting state agency shall pay interest to the
contractor equivalent to the legal rate set forth in subdivision (a)
of Section 685.010 of the Code of Civil Procedure. In the event that
the payment is not made within 30 days of receipt of the contractor's
request or the first submittal by the engineer, and the contracting
state agency has processed the payment within 16 days after receipt
of the request or submittal, the Controller shall pay interest as
provided in Section 685.010 of the Code of Civil Procedure.
   For purposes of this section, a payment request shall be
considered properly executed if funds are available for payment of
the payment request, and payment is not delayed due to an audit
inquiry by the Controller. 
   (b) 
    (c)  Upon receipt of a payment request, each agency
shall require:
   (1) That each payment request be reviewed as soon as practicable
after receipt for the purpose of determining that a payment request
is a proper payment request.
   (2) Any payment request determined not to be a proper payment
request suitable for payment shall be returned as soon as
practicable, but not later than seven days, after receipt, specifying
the reasons that the payment request is not a proper payment
request.
   (3) The number of days available to a state agency to make a
timely payment of payment request without incurring interest shall be
reduced by the number of days by which an agency exceeds the
requirements of paragraph (2).