A BILL TO BE ENTITLED
|
|
AN ACT
|
|
relating to appropriations of water for use in aquifer storage and |
|
recovery projects. |
|
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: |
|
SECTION 1. Section 11.153, Water Code, is amended by |
|
amending Subsection (c) and adding Subsections (d), (e), and (f) to |
|
read as follows: |
|
(c) The [This section does not preclude the] commission may |
|
consider [from considering] an aquifer storage and recovery project |
|
to be a component of a project permitted under this chapter that is |
|
not required to be based on the continuous availability of |
|
historic, normal stream flow. |
|
(d) An aquifer storage and recovery project may involve the |
|
use of water derived from multiple sources, including a new |
|
appropriation of water. Except as provided by Subsection (e), a |
|
water right or an amendment to a water right authorizing a new |
|
appropriation of water for use in an aquifer storage and recovery |
|
project: |
|
(1) must include any special conditions the commission |
|
considers necessary to implement this section; |
|
(2) may be for water that is not continuously |
|
available; |
|
(3) may authorize the diversion and use of excess |
|
flows in a watercourse or stream that would otherwise flow into the |
|
Gulf of Mexico; and |
|
(4) may not interfere with or negatively affect: |
|
(A) existing water rights in the same river basin |
|
as the diversion point for the new appropriation; or |
|
(B) applicable environmental flow standards |
|
adopted under Section 11.1471. |
|
(e) Before approving an application for a water right or an |
|
amendment to a water right for a new appropriation of water in the |
|
Rio Grande basin for an aquifer storage and recovery project, the |
|
commission shall consider the water accounting requirements for any |
|
international water sharing treaty, minutes, and agreement |
|
applicable to the Rio Grande basin and the effect of the project on |
|
the allocation of water by the Rio Grande watermaster in the middle |
|
and lower Rio Grande. The commission may not authorize a new |
|
appropriation of water that would result in a violation of a treaty |
|
or court decision. |
|
(f) The commission may adopt rules providing an expedited |
|
procedure for acting on an application for a water right or an |
|
amendment to a water right under this section. |
|
SECTION 2. Subchapter D, Chapter 11, Water Code, is amended |
|
by adding Section 11.156 to read as follows: |
|
Sec. 11.156. AMENDMENT TO CONVERT USE FROM RESERVOIR |
|
STORAGE TO AQUIFER STORAGE AND RECOVERY. (a) In this section, |
|
"aquifer storage and recovery project" has the meaning assigned by |
|
Section 27.151. |
|
(b) A holder of a water right authorizing an appropriation |
|
of water for storage in a storage reservoir that has not been |
|
constructed may file an application for an amendment to the water |
|
right to change the use or purpose for which the appropriation is to |
|
be made to storage in an aquifer as part of an aquifer storage and |
|
recovery project. |
|
(c) An application for an amendment to a water right |
|
described by Subsection (b) may request an increase in the amount of |
|
water that may be diverted or the rate of diversion on the basis of |
|
an evaporation credit that takes into account the amount of water |
|
that would have evaporated if the storage reservoir had been |
|
constructed. |
|
(d) An application for an amendment to a water right |
|
described by Subsection (b): |
|
(1) is exempt from any notice and hearing requirements |
|
of a statute, commission rule, or permit condition and may not be |
|
referred to the State Office of Administrative Hearings for a |
|
contested case hearing if the application does not request: |
|
(A) an increase in the amount of water that may be |
|
diverted or the rate of diversion; or |
|
(B) a change in the diversion point; and |
|
(2) is subject to the notice and hearing requirements |
|
of this chapter if the application requests: |
|
(A) an increase in the amount of water that may be |
|
diverted or the rate of diversion, including an increase on the |
|
basis of an evaporation credit; or |
|
(B) a change in the diversion point. |
|
(e) If the commission grants an application for an amendment |
|
to a water right described by Subsection (d)(2), the commission |
|
shall include in the amendment any special conditions the |
|
commission considers necessary to: |
|
(1) protect existing water rights; and |
|
(2) comply with any applicable environmental flow |
|
standards established under Section 11.1471. |
|
(f) The commission may adopt rules providing an expedited |
|
procedure for acting on an application for an amendment to a water |
|
right described by Subsection (b). |
|
SECTION 3. This Act takes effect immediately if it receives |
|
a vote of two-thirds of all the members elected to each house, as |
|
provided by Section 39, Article III, Texas Constitution. If this |
|
Act does not receive the vote necessary for immediate effect, this |
|
Act takes effect December 1, 2017. |