88R22860 DIO-F
 
  By: Darby, Guillen, Hernandez, Slawson, H.B. No. 2848
      Burrows
 
  Substitute the following for H.B. No. 2848:
 
  By:  Smithee C.S.H.B. No. 2848
 
 
 
A BILL TO BE ENTITLED
 
AN ACT
  relating to the approval of a certificate of public convenience and
  necessity for certain transmission projects.
         BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
         SECTION 1.  Section 37.056, Utilities Code, is amended by
  amending Subsections (c-1) and (d) and adding Subsections (d-1) and
  (d-2) to read as follows:
         (c-1)  In considering the need for additional service under
  Subsection (c)(2) for a reliability transmission project that
  serves the ERCOT power region, the commission must consider the
  historical load, forecasted load growth, and additional load
  currently seeking interconnection, including load for which the
  electric utility has yet to sign an interconnection agreement, as
  determined by the electric utility with the responsibility for
  serving the load.
         (d)  The commission by rule shall establish criteria, in
  addition to the criteria described by Subsection (c), for granting
  a certificate for a transmission project that serves the ERCOT
  power region, that is not necessary to meet state or federal
  reliability standards, and that is not included in a plan developed
  under Section 39.904(g).  [The criteria must include a comparison
  of the estimated cost of the transmission project for consumers and
  the estimated congestion cost savings for consumers that may result
  from the transmission project, considering both current and future
  expected congestion levels and the transmission project's ability
  to reduce those congestion levels.] The commission shall include
  with its decision on an application for a certificate to which this
  subsection applies findings on the criteria. The criteria must:
               (1)  include a comparison of the estimated cost of the
  transmission project to consumers and the estimated congestion cost
  savings for consumers that may result from the project, considering
  both current and expected congestion levels and the project's
  ability to reduce those levels;
               (2)  address:
                     (A)  other benefits of the transmission project,
  including deferral of reliability upgrade costs, reduction of
  transmission system losses, and reduction of operating reserve
  costs;
                     (B)  solutions to relieve generic transmission
  constraints;
                     (C)  potential for increasing transmission system
  reliability, resiliency, and operational flexibility;
                     (D)  potential for minimizing outage moratoria
  and transmission system congestion by employing planning criteria
  that include contingencies for a planned outage followed by an
  unplanned outage under peak conditions; and
                     (E)  the operational benefits and reduced impacts
  on affected landowners of constructing new transmission lines
  operating at or below 345 kilovolts as double circuit capable
  lines;
               (3)  evaluate:
                     (A)  the costs of the transmission project on a
  levelized basis over the life of the project; and
                     (B)  the benefits of the transmission project on a
  levelized basis over the life of the project or the longest period
  determined to be reasonable by the commission; and
               (4)  in high growth areas and areas experiencing or
  expected to experience rapid growth in power demand, including
  coastal regions, oil and gas producing, processing, or refining
  regions, and semiconductor manufacturing regions, prioritize the
  development of additional and sufficient transmission capacity to
  provide flexibility to serve new load.
         (d-1)  For a transmission project described by Subsection
  (d), the commission shall require all new transmission lines
  operating at or below 345 kilovolts to be constructed as double
  circuit capable lines unless the electric utility requests an
  exception.
         (d-2)  For a transmission project described by Subsection
  (d)(4), the applicant for the transmission project certificate
  shall submit a copy of the application to the independent
  organization certified under Section 39.151 for the ERCOT power
  region.  The independent organization shall review and provide the
  commission with the organization's recommendations regarding the
  application not later than the 90th day after the date the
  application is received.  If the organization fails to provide the
  commission with its recommendations before the 91st day after the
  date the application is received, the commission shall consider the
  transmission project to be a project that meets the need for
  additional service under this section.
         SECTION 2.  Section 37.057, Utilities Code, is amended to
  read as follows:
         Sec. 37.057.  DEADLINE FOR APPLICATION FOR NEW TRANSMISSION
  FACILITY. The commission must approve or deny an application for a
  certificate for a new transmission facility not later than the
  181st day after [the first anniversary of] the date the application
  is filed. If the commission does not approve or deny the
  application on or before that date, a party may seek a writ of
  mandamus in a district court of Travis County to compel the
  commission to decide on the application.
         SECTION 3.  The changes in law made by this Act apply only to
  a proceeding affecting a certificate of public convenience and
  necessity that commences on or after the effective date of this Act.
  A proceeding affecting a certificate of public convenience and
  necessity that commenced before the effective date of this Act is
  governed by the law in effect on the date the proceeding is
  commenced, and that law is continued in effect for that purpose.
         SECTION 4.  This Act takes effect immediately if it receives
  a vote of two-thirds of all the members elected to each house, as
  provided by Section 39, Article III, Texas Constitution.  If this
  Act does not receive the vote necessary for immediate effect, this
  Act takes effect September 1, 2023.