Bill Text: VA SB698 | 2018 | Regular Session | Comm Sub
Bill Title: Erosion and sediment control; inspections of natural gas pipelines, stop work instructions.
Spectrum: Partisan Bill (Democrat 4-0)
Status: (Passed) 2018-03-10 - Governor: Acts of Assembly Chapter text (CHAP0297) [SB698 Detail]
Download: Virginia-2018-SB698-Comm_Sub.html
Be it enacted by the General Assembly of Virginia:
1. That the Code of Virginia is amended by adding a section numbered 62.1-44.15:58.1 as follows:
§62.1-44.15:58.1. Inspections; land-disturbing activities of natural gas pipelines; stop work instructions.
A. The Department is authorized to conduct inspections of the land-disturbing activities of interstate and intrastate natural gas pipeline companies that have approved annual standards and specifications pursuant to § 62.1-44.15:55 as such land-disturbing activities relate to construction of any natural gas transmission pipeline greater than 36 inches in diameter to determine (i) compliance with such annual standards and specifications, (ii) compliance with any site-specific plans, and (iii) if there have been or are likely to be adverse impacts to water quality as a result of such land-disturbing activities. When the Department determines that there has been a substantial adverse impact to water quality or that an imminent and substantial adverse impact to water quality is likely to occur as a result of such land-disturbing activities, the Department may issue a stop work instruction, without advance notice or hearing, requiring that all or part of such land-disturbing activities on the site be stopped until corrective measures specified in the stop work instruction have been completed and approved by the Department.
Such stop work instruction shall become effective upon service on the company by email or other technology agreed to in writing by the Department and the company, by mailing with confirmation of delivery to the address specified in the annual standards and specifications, if available, or by delivery at the site to a person previously identified to the Department by the company.
B. Within 10 business days of issuance of a stop work instruction, the Department shall promptly provide to such company an opportunity for an informal fact-finding proceeding. Reasonable notice as to the time and place of the informal fact-finding proceeding shall be provided to such company. Within 10 business days of the informal fact-finding proceeding, the Department shall affirm, modify, amend, or cancel such stop work instruction. Upon written documentation from the company of the completion and approval by the Department in writing of the corrective measures specified in the stop work instruction, the instruction shall be immediately lifted.
C. The company may appeal such stop work instruction to the circuit court of the jurisdiction wherein the land-disturbing activities subject to the stop work instruction occurred, or to another appropriate court, in accordance with the requirements of the Administrative Process Act (§ 2.2-4000 et seq.). Any person violating or failing, neglecting, or refusing to obey a stop work instruction issued by the Department may be compelled in a proceeding instituted in the circuit court of the jurisdiction wherein the violation was alleged to have occurred or other appropriate court to obey same and to comply therewith by injunction, mandamus, or other appropriate remedy. Nothing in this section shall prevent the Board or the Department from taking any other action authorized by this chapter.
2. That an emergency exists and this act is in force from its passage.