Bill Text: HI HB1191 | 2012 | Regular Session | Introduced
Bill Title: CIP; 50th Representative District
Spectrum: Partisan Bill (Republican 1-0)
Status: (Introduced - Dead) 2011-12-01 - Carried over to 2012 Regular Session. [HB1191 Detail]
Download: Hawaii-2012-HB1191-Introduced.html
HOUSE OF REPRESENTATIVES |
H.B. NO. |
1191 |
TWENTY-SIXTH LEGISLATURE, 2011 |
|
|
STATE OF HAWAII |
|
|
|
|
|
|
||
|
A BILL FOR AN ACT
RELATING TO CAPITAL IMPROVEMENT PROJECTS FOR THE BENEFIT OF THE fiftieth REPRESENTATIVE DISTRICT.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The director of finance is authorized to issue general obligation bonds in the sum of $ or so much thereof as may be necessary and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2011-2012 for the purpose of financing the capital improvement projects listed in this Act.
I. To be expended by the Department of Education:
A. Aikahi Elementary School, Oahu
(1) Campus-wide electrical upgrade.
Plans $1,000
Design $1,000
Construction $1,498,000
Total Funding $1,500,000
(2) Upgrading of telephone system, repair the roof of building D, and renovation of the cafeteria and bathrooms.
Plans $1,000
Design $1,000
Construction $123,000
Total Funding $125,000
B. Kailua Elementary School, Oahu
(1) Grading, resurfacing, and restriping of the parking lot.
Design $32,000
Construction $172,000
Total Funding $204,000
C. Kailua Intermediate School, Oahu
(1) Campus-wide electrical upgrade.
Design $91,600
Construction $824,400
Total Funding $916,000
(2) Design and construction for the renovation of locker room/shower facilities.
Design $80,000
Construction $1,420,000
Total Funding $1,500,000
D. Kainalu Elementary School, Oahu
(1) Campus-wide electrical upgrade.
Design and construction $1,500,000
Total Funding $1,500,000
(2) Repair of covered walkway between buildings D & E and extending to the cafeteria.
Design $35,000
Construction $200,000
Total Funding $235,000
E. Kalaheo High School, Oahu
(1) Replace traditional locks with electronic key cards.
Design & Construction $500,000
Total Funding $500,000
(2) Plan, design, construction, and equipment for a regulation football/soccer field, lengthen the physical education field and install field lights and bleachers.
Plans $75,000
Design $75,000
Construction $350,000
Equipment $250,000
Total Funding $750,000
F. Mokapu Elementary School, Oahu
(1) Replacement of playground equipment.
Construction & equipment $150,000
Total Funding $150,000
(2) Electrical upgrade for the entire campus.
Design $120,000
Construction & equipment $1,080,000
Total Funding $1,200,000
SECTION 2. The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agency for the purposes of this Act.
SECTION 3. The appropriation made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal biennium for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2014, shall lapse as of that date.
SECTION 4. This Act shall take effect on July 1, 2011.
INTRODUCED BY: |
_____________________________ |
|
|
Report Title:
CIP; 50th Representative District
Description:
Appropriates funds for capital improvement projects for the benefit of the 50th representative district
The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.