Bill Text: HI HB1953 | 2020 | Regular Session | Introduced


Bill Title: Relating To The Capital Improvement Projects For The Benefit Of The Thirty-sixth Representative District.

Spectrum: Partisan Bill (Republican 1-0)

Status: (Introduced - Dead) 2020-01-23 - Referred to FIN, referral sheet 4 [HB1953 Detail]

Download: Hawaii-2020-HB1953-Introduced.html

HOUSE OF REPRESENTATIVES

H.B. NO.

1953

THIRTIETH LEGISLATURE, 2020

 

STATE OF HAWAII

 

 

 

 

 

 

A BILL FOR AN ACT

 

 

 

RELATING TO THE CAPITAL IMPROVEMENT PROJECTS FOR THE BENEFIT OF THE THIRTY-SIXTH REPRESENTATIVE DISTRICT.

 

 

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

 


     SECTION 1.  The director of finance is authorized to issue general obligation bonds in the sum of $32,421,000 or so much thereof as may be necessary and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2020-2021 for the purposes of financing capital improvement projects for the thirty-sixth representative district, as follows:

     1.  To be expended by the department of education:

     A.  Kipapa elementary school, Oahu

        Plans, design, and construction to reroof campus portable buildings and building D.

        Plans                                        $3,000

        Design                                       $3,000

        Construction                               $362,000

        Total funding                              $368,000

     B.  Kipapa elementary school, Oahu

        Plans, design, construction, and equipment to repair transformer room and install campus ceiling fans.

        Plans                                        $3,000

        Design                                       $3,000

        Construction                               $364,000

        Equipment                                     3,000

        Total funding                              $373,000

     C.  Mililani high school, Oahu

        Plans, design, and construction to reroof buildings C, F, G, R and W.

        Plans                                        $2,000

        Design                                       $2,000

        Construction                             $1,962,000

        Total funding                            $1,966,000

     D.  Mililani high school, Oahu

        Plans, design, and construction to renovate science classroom, replace book lockers, and renovate toilets in building B.

        Plans                                        $9,000

        Design                                       $9,000

        Construction                               $945,000

        Total funding                              $963,000

     E.  Mililani Ike elementary school, Oahu

        Plans, design, and construction to repaint exterior of buildings A and C.

        Plans                                        $4,000

        Design                                       $4,000

        Construction                               $414,000

        Total funding                              $422,000

     F.  Mililani Ike elementary school, Oahu

        Plans, design, and construction to resurface cafeteria parking lot, and repair covered playcourt.

        Plans                                       $12,000

        Design                                      $12,000

        Construction                             $1,210,000

        Total funding                            $1,234,000

     G.  Mililani Ike elementary school, Oahu

        Plans, design, equipment, and construction to replace the bell and public announcement system.

        Plans                                       $25,000

        Design                                      $25,000

        Equipment                                   $25,000

        Construction                               $300,000

        Total funding                              $375,000

     H.  Mililani Mauka elementary school, Oahu

        Plans, design, and construction to reroof building D and repair campus irrigation system.

        Plans                                       $11,000

        Design                                      $11,000

        Construction                             $1,100,000

        Total funding                            $1,122,000

     I.  Mililani middle school, Oahu

        Plans, design, and construction to replace folding doors in buildings B, C and F.

        Plans                                        $8,000

        Design                                       $8,000

        Construction                               $780,000

        Total funding                              $796,000

     J.  Mililani middle school, Oahu

        Plans, design, and construction to replace air conditioning units.

        Plans                                        $3,000

        Design                                       $3,000

        Construction                               $336,000

        Total funding                              $342,000

     K.  Mililani middle school, Oahu

        Plans, design, and construction to replace exterior soffits on buildings C and E.

        Plans                                        $7,000

        Design                                       $7,000

        Construction                               $720,000

        Total funding                              $734,000

     L.  Mililani Waena elementary school, Oahu

        Plans, design, and construction to add electrical circuits in building D, and install ceiling fans in building F.

        Plans                                        $2,000

        Design                                       $2,000

        Construction                               $232,000

        Total funding                              $236,000

     M.  Mililani Waena elementary school, Oahu

        Plans, design, and construction for campus structural repair phase 2, and campus concrete repairs.

        Plans                                        $5,000

        Design                                       $5,000

        Construction                               $480,000

        Total funding                              $490,000

     2.  To be expended by the department of transportation:

     A.  H-2 freeway, Oahu

        Plans, design, and construction to add an additional lane and double-loop on-ramp southbound from Mililani Mauka with a pedestrian overpass; traffic mitigation; and ground and site improvements.

        Plans                                    $1,500,000

        Design                                   $1,500,000

        Construction                            $20,000,000

        Total funding                           $23,000,000

     SECTION 2.  The appropriation made for the capital

improvement projects authorized by this Act shall not lapse at the end of the fiscal biennium for which the appropriation unencumbered as of June 30, 2022, shall lapse as of that date.

SECTION 3.  The sum appropriated shall be expended by the designated expending agency for the purposes of this Act.

SECTION 4.  This Act shall take effect on July 1, 2020.

 

INTRODUCED BY:

_____________________________

 

 


 


 

Report Title:

CIP, 36th Representative District; Appropriation

 

Description:

Authorizes issuance of general obligation bonds and appropriates moneys for capitol improvement projects in the 36th representative district.

 

 

 

The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.

feedback