A BILL FOR AN ACT
relating to capital improvement projects for the benefit of the thirty-first representative district.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2012-2013.
1. To be expended by the department of education:
A. Moanalua high school, Oahu
Design and construction of athletic field turf.
Design $300,000
Construction $2,000,000
Total funding $2,300,000
B. Moanalua high school, Oahu
Design and construction of all-weather athletic
track.
Design $450,000
Construction $3,000,000
Total funding $3,450,000
C. Moanalua high school, Oahu
Design, construction, and equipment for
performing arts center phase II.
Design $4,000,000
Construction $24,000,000
Equipment $1,000,000
Total funding $29,000,000
D. Moanalua middle school, Oahu
Design and construction for air-conditioning
expansion in buildings B and F.
Design $200,000
Construction $1,000,000
Total funding $1,200,000
E. Moanalua middle school, Oahu
Design and construction for a new media
technology center and renovations to existing
computer labs; ground and site improvements;
equipment and appurtenances.
Design $400,000
Construction $4,450,000
Equipment $150,000
Total funding $5,000,000
F. Aliamanu middle school, Oahu
Design and construction for a physical education
running surface; ground and site improvements;
equipment and appurtenances.
Design $20,000
Construction $180,000
Total funding $200,000
G. Moanalua elementary school, Oahu
Design, construction, and equipment for a new
technology center as an expansion of the library
or new building; ground and site improvements;
equipment and appurtenances.
Design $150,000
Construction $1,970,000
Equipment $30,000
Total funding $2,150,000
H. Moanalua elementary school, Oahu
Design and construction for parking safety
improvements, including additional parking and
new drop-off lane; ground and site improvements;
equipment and appurtenances.
Design $30,000
Construction $300,000
Total funding $330,000
I. Salt Lake elementary school, Oahu
Interior renovation and construction of
Classroom C-1, including central air-
conditioning, electrical upgrades, classroom
equipment, and video and data connectivity.
Design $200,000
Construction $600,000
Equipment $200,000
Total funding $1,000,000
J. Salt Lake elementary school, Oahu
Interior renovation and construction of
Classroom E-3, including central air-
conditioning, electrical upgrades, classroom
equipment, and video and data connectivity.
Design $200,000
Construction $600,000
Equipment $200,000
Total funding $1,000,000
K. Salt Lake elementary school, Oahu
Interior renovation and construction of
Classroom E-4, including central air-
conditioning, electrical upgrades, classroom
equipment, and video and data connectivity.
Design $200,000
Construction $600,000
Equipment $200,000
Total funding $1,000,000
L. Aliamanu elementary school, Oahu
Design, construction, and equipment for the
expansion of the administration building; ground
and site improvements; equipment and
appurtenances.
Design $400,000
Construction $3,075,000
Equipment $25,000
Total funding $3,500,000
M. Aliamanu elementary school, Oahu
Design, construction, and equipment for the expansion of the library; ground and site improvements; equipment and appurtenances.
Design $500,000
Construction $4,460,000
Equipment $40,000
Total funding $5,000,000
SECTION 2. The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agency for the purposes of this Act.
SECTION 3. This Act shall take effect on July 1, 2012.
INTRODUCED BY: |
_____________________________ |
|
|
Report Title:
Capital Improvement Projects; Thirty-first Representative District Schools; Appropriation
Description:
Appropriates funds for capital improvement projects for schools in the Thirty-first Representative District. Effective July 1, 2012.
The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.