A BILL FOR AN ACT
relating to capital improvement projects for the benefit of THE Thirteenth SENATORIAL DISTRICT.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The director of finance is authorized to issue general obligation bonds in the sum of $22,609,261 or so much thereof as may be necessary and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2019-2020 for the purpose of capital improvement projects for the thirteenth senatorial district, as follows:
Equipment for systems to increase luminosity and visual acuity, bring areas of the building up to safety code and egress standards, and reduce power consumption.
Equipment $648,061
Total funding $648,061
The sum appropriated for this capital improvement project shall be expended by the city and county of Honolulu.
2. Central middle school
Equipment for replacing stage lighting in building B.
Equipment $120,000
Total funding $120,000
The sum appropriated for this capital improvement project shall be expended by the department of accounting and general services.
3. Central middle school
Equipment for installing ceiling fans in building B cafeteria.
Equipment $40,000
Total funding $40,000
The sum appropriated for this capital improvement project shall be expended by the department of accounting and general services.
4. Central middle school
Equipment for replacing house lighting in building B auditorium.
Equipment $100,000
Total funding $100,000
The sum appropriated for this capital improvement project shall be expended by the department of accounting and general services.
5. Central middle school
Land for campus beautification.
Land $20,000
Total funding $20,000
The sum appropriated for this capital improvement project shall be expended by the department of accounting and general services.
6. Kauluwela elementary school
Construction for installing walls between various classrooms in buildings S and D.
Construction $200,000
Total funding $200,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
7. Kauluwela elementary school
Construction for repair of the stage area under the tree shared between the school and adjacent community park.
Construction $500,000
Total funding $500,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
8. Kauluwela elementary school
Construction for installation of a student playground behind building D.
Construction $250,000
Total funding $250,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
9. Kauluwela elementary school
Construction for paving the dirt parking lot area shared between the school and adjacent community park.
Construction $200,000
Total funding $200,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
10. McKinley high school
Construction for addition of lights, bleachers, and ticket booth for athletic field and track.
Construction $2,000,000
Total funding $2,000,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
11. McKinley high school
Plans, design, and construction for cleaning and painting of building exteriors, providing concrete exteriors stairs and walkways, and providing irrigation systems and landscape improvements of historic buildings A, B, C, D, and E.
Plans $500,000
Design $500,000
Construction $2,500,000
Total funding $3,500,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
12. McKinley high school
Plans, design, and construction for general improvements to historic mall and buildings to promote academy environment.
Plans $500,000
Design $500,000
Construction $2,000,000
Total funding $3,000,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
13. McKinley high school
Plans, design, construction, and equipment for general improvements to baseball field, including installation of concrete sidewalks; paved parking lot; sprinkler system; new field, dugout, and storage areas; and electronic scoreboard.
Plans $50,000
Design $200,000
Construction $2,000,000
Equipment $50,000
Total funding $2,300,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
14. McKinley high school
Plans, design, construction, and equipment for installation of ceiling fans in historic building F.
Plans $500,000
Design $500,000
Construction $800,000
Equipment $6,200
Total funding $1,806,200
The sum appropriated for this capital improvement project shall be expended by the department of education.
15. McKinley high school
Plans, design, construction, and equipment for improvements and expansion of usable area in M. M. Scott auditorium.
Plans $50,000
Design $200,000
Construction $2,000,000
Equipment $50,000
Total funding $2,300,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
16. McKinley high school
Plans, design, construction, and equipment for installation of an electronic marquee at the corner of King street and Pensacola street.
Plans $100,000
Design $100,000
Construction $300,000
Equipment $50,000
Total funding $550,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
17. McKinley high school
Plans, design, construction, and equipment for installation of a sound system in the gymnasium.
Plans $10,000
Design $10,000
Construction $30,000
Equipment $50,000
Total funding $100,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
18. McKinley high school
Plans, design, construction, and equipment for creation of twenty-first century learning spaces through renovation of existing classroom spaces for digital media, design and innovation, and exhibition.
Plans $100,000
Design $100,000
Construction $1,000,000
Equipment $50,000
Total funding $1,250,000
The sum appropriated for this capital improvement project shall be expended by the department of education.
19. Maluhia
Design and construction for air conditioning system repairs to cooling tower, air handlers, and chiller.
Design $50,000
Construction $450,000
Total funding $500,000
The sum appropriated for this capital improvement project shall be expended by the department of health.
20. Maluhia
Design and construction for replacement of central air conditioning system on the second floor with a multi-zone split system.
Design $115,000
Construction $885,000
Total funding $1,000,000
The sum appropriated for this capital improvement project shall be expended by the department of health.
21. AMP 34 and 35
Design for installation of photovoltaic panels.
Design $150,000
Total funding $150,000
The sum appropriated for this capital improvement project shall be expended by the Hawaii public housing authority.
22. AMP 34 and 35
Design for installation of security cameras at the elevator cabs and lobbies.
Design $100,000
Total funding $100,000
The sum appropriated for this capital improvement project shall be expended by the Hawaii public housing authority.
23. Kalanihuia, site improvements, security and accessibility
Design for security and accessibility for the elderly, plumbing and drainage systems, and site improvements.
Design $1,000,000
Total funding $1,000,000
The sum appropriated for this capital improvement project shall be expended by the Hawaii public housing authority.
24. Makamae, site improvements, security, and drainage
Design for security, plumbing, and drainage systems.
Design $200,000
Total funding $200,000
The sum appropriated for this capital improvement project shall be expended by the Hawaii public housing authority.
25. Puahala homes, building improvements phase IV
Design and construction for spall and exterior repairs.
Design $75,000
Construction $400,000
Total funding $475,000
The sum appropriated for this capital improvement project shall be expended by the Hawaii public housing authority.
26. Domestic Violence Action Center
Land for expanded office space.
Land $300,000
Total funding $300,000
The sum appropriated for this capital improvement project shall be expended by the Judiciary.
SECTION 2. The appropriation made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal year for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2022, shall lapse as of that date.
SECTION 3. This Act shall take effect on July 1, 2019.
INTRODUCED BY: |
_____________________________ |
|
|
|
|
|
|
|
|
Report Title:
CIP; Thirteenth Senatorial District; Appropriation
Description:
Appropriates funds for capital improvement projects in the thirteenth senatorial district.
The summary description
of legislation appearing on this page is for informational purposes only and is
not legislation or evidence of legislative intent.