Bill Text: TX HB533 | 2025-2026 | 89th Legislature | Introduced
Bill Title: Relating to imposing liens for labor and supplies provided by cleaners.
Spectrum: Partisan Bill (Democrat 1-0)
Status: (Introduced) 2024-11-12 - Filed [HB533 Detail]
Download: Texas-2025-HB533-Introduced.html
89R908 PRL-D | ||
By: Cortez | H.B. No. 533 |
|
||
|
||
relating to imposing liens for labor and supplies provided by | ||
cleaners. | ||
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | ||
SECTION 1. Sections 53.001(2) and (4), Property Code, are | ||
amended to read as follows: | ||
(2) "Improvement" includes: | ||
(A) a house, building, structure, parking | ||
structure, physical appurtenance, pool, utility, railroad, well, | ||
storage facility, abutting sidewalks and streets, utilities in or | ||
on those sidewalks and streets, land reclaimed from overflow, and | ||
other fixtures or modifications to real property; | ||
(B) clearing, grubbing, draining, or fencing of | ||
land; | ||
(C) machinery or apparatuses used for raising | ||
water or for supplying or storing water for stock, domestic use, or | ||
irrigation; | ||
(D) work described by Section 53.021(4) or (6); | ||
and | ||
(E) a design, drawing, plan, plat, survey, or | ||
specification provided by a licensed architect, engineer, or | ||
surveyor. | ||
(4) "Material" means all or part of: | ||
(A) the material, machinery, fixtures, or tools: | ||
(i) incorporated into the work; | ||
(ii) used in the direct performance of the | ||
work; | ||
(iii) specially fabricated for an | ||
improvement; or | ||
(iv) ordered and delivered for | ||
incorporation or use; | ||
(B) rent at a reasonable rate and actual running | ||
repairs at a reasonable cost for construction equipment used or | ||
reasonably required and delivered for use in the direct performance | ||
of the work at the site of the construction or repair; or | ||
(C) power, water, fuel, [ |
||
cleaning supplies consumed or ordered and delivered for consumption | ||
in the direct performance of the work. | ||
SECTION 2. Section 53.021, Property Code, is amended to | ||
read as follows: | ||
Sec. 53.021. PERSONS ENTITLED TO LIEN. A person has a lien | ||
if the person, under a contract with the owner or the owner's agent, | ||
trustee, receiver, contractor, or subcontractor: | ||
(1) labors or furnishes labor or materials for | ||
construction or repair of an improvement; | ||
(2) specially fabricates material, even if the | ||
material is not delivered; | ||
(3) is a licensed architect, engineer, or surveyor | ||
providing services to prepare a design, drawing, plan, plat, | ||
survey, or specification; | ||
(4) provides labor, plant material, or other supplies | ||
for the installation of landscaping for an improvement, including | ||
the construction of a retention pond, retaining wall, berm, | ||
irrigation system, fountain, or other similar installation; [ |
||
(5) performs labor as part of, or furnishes labor or | ||
materials for, the demolition of an improvement on real property; | ||
or | ||
(6) provides labor or other supplies for the interior | ||
cleaning of a home or office. | ||
SECTION 3. Section 53.023, Property Code, is amended to | ||
read as follows: | ||
Sec. 53.023. PAYMENT SECURED BY LIEN. The lien secures | ||
payment for: | ||
(1) the labor done or material furnished for the | ||
construction, repair, design, survey, [ |
||
cleaning; or | ||
(2) the specially fabricated material, even if the | ||
material has not been delivered or incorporated into the | ||
construction or repair, less its fair salvage value. | ||
SECTION 4. Section 53.124(e), Property Code, is amended to | ||
read as follows: | ||
(e) The time of inception of a lien that is created under | ||
Section 53.021(3), (4), (5), or (6) [ |
||
date of recording of an affidavit of lien under Section 53.052. The | ||
priority of a lien claimed by a person entitled to a lien under | ||
Section 53.021(3), (4), (5), or (6) [ |
||
respect to other mechanic's liens is determined by the date of | ||
recording. A lien created under Section 53.021(3), (4), (5), or (6) | ||
[ |
||
grantee or purchaser who acquires an interest in the real property | ||
before the time of inception of the lien. | ||
SECTION 5. The changes in law made by this Act apply only to | ||
an original contract entered into on or after the effective date of | ||
this Act. An original contract entered into before the effective | ||
date of this Act is governed by the law as it existed immediately | ||
before the effective date of this Act, and that law is continued in | ||
effect for that purpose. | ||
SECTION 6. This Act takes effect September 1, 2025. |