Bill Text: TX HB837 | 2021-2022 | 87th Legislature | Enrolled
Bill Title: Relating to the procedure for amending or revoking certificates of public convenience and necessity issued to certain retail public utilities.
Spectrum: Partisan Bill (Democrat 2-0)
Status: (Passed) 2021-06-04 - Effective on 9/1/21 [HB837 Detail]
Download: Texas-2021-HB837-Enrolled.html
H.B. No. 837 |
|
||
relating to the procedure for amending or revoking certificates of | ||
public convenience and necessity issued to certain retail public | ||
utilities. | ||
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | ||
SECTION 1. Section 13.254(a-3), Water Code, is amended to | ||
read as follows: | ||
(a-3) Within 60 calendar days from the date the utility | ||
commission determines the petition filed pursuant to Subsection | ||
(a-1) to be administratively complete, the utility commission shall | ||
grant the petition unless the utility commission makes an express | ||
finding that the petitioner failed to satisfy the elements required | ||
in Subsection (a-1) and supports its finding with separate findings | ||
and conclusions for each element based solely on the information | ||
provided by the petitioner and the certificate holder. The utility | ||
commission may grant or deny a petition subject to terms and | ||
conditions specifically related to the service request of the | ||
petitioner and all relevant information submitted by the petitioner | ||
and the certificate holder. In addition, the utility commission may | ||
require an award of compensation as otherwise provided by this | ||
section. If the utility commission requires an award of | ||
compensation, the utility commission shall require the petitioner | ||
to submit a report to the utility commission verifying for the | ||
purposes of Subsection (d) that the compensation has been paid to | ||
the decertified retail public utility. | ||
SECTION 2. Section 13.2541(f), Water Code, is amended to | ||
read as follows: | ||
(f) The utility commission may require an award of | ||
compensation by the petitioner to the certificate holder in the | ||
manner provided by this section. If the utility commission requires | ||
an award of compensation, the utility commission shall require the | ||
petitioner to submit a report to the utility commission verifying | ||
for the purposes of Subsection (j) that the compensation has been | ||
paid to the certificate holder. | ||
SECTION 3. Section 13.255, Water Code, is amended by | ||
amending Subsection (c) and adding Subsections (c-1) and (c-2) to | ||
read as follows: | ||
(c) The utility commission shall grant single certification | ||
to the municipality. The utility commission shall also determine | ||
whether single certification as requested by the municipality would | ||
result in property of a retail public utility being rendered | ||
useless or valueless to the retail public utility, and shall | ||
determine in its order the monetary amount that is adequate and just | ||
to compensate the retail public utility for such property. If the | ||
municipality in its application has requested the transfer of | ||
specified property of the retail public utility to the municipality | ||
or to a franchised utility, the utility commission shall also | ||
determine in its order the adequate and just compensation to be paid | ||
for such property pursuant to the provisions of this section, | ||
including an award for damages to property remaining in the | ||
ownership of the retail public utility after single certification. | ||
The order of the utility commission shall not be effective to | ||
transfer property. A transfer of property may only be obtained | ||
under this section by a court judgment rendered pursuant to | ||
Subsection (d) or (e). The grant of single certification by the | ||
utility commission shall go into effect on the date the | ||
municipality or franchised utility, as the case may be, pays | ||
adequate and just compensation pursuant to court order, or pays an | ||
amount into the registry of the court or to the retail public | ||
utility under Subsection (f). If the court judgment provides that | ||
the retail public utility is not entitled to any compensation, the | ||
grant of single certification shall go into effect when the court | ||
judgment becomes final. | ||
(c-1) The utility commission by rule shall require the | ||
municipality or franchised utility to submit a report to the | ||
utility commission verifying that the municipality or franchised | ||
utility has paid all required adequate and just compensation to the | ||
retail public utility as provided by Subsection (c). | ||
(c-2) The municipality or franchised utility must provide | ||
to each customer of the retail public utility being acquired an | ||
individual written notice within 60 days after the effective date | ||
for the transfer specified in the court judgment. The notice must | ||
clearly advise the customer of the identity of the new service | ||
provider, the reason for the transfer, the rates to be charged by | ||
the new service provider, and the effective date of those rates. | ||
SECTION 4. This Act takes effect September 1, 2021. | ||
______________________________ | ______________________________ | |
President of the Senate | Speaker of the House | |
I certify that H.B. No. 837 was passed by the House on April | ||
16, 2021, by the following vote: Yeas 142, Nays 3, 2 present, not | ||
voting. | ||
______________________________ | ||
Chief Clerk of the House | ||
I certify that H.B. No. 837 was passed by the Senate on May | ||
19, 2021, by the following vote: Yeas 31, Nays 0. | ||
______________________________ | ||
Secretary of the Senate | ||
APPROVED: _____________________ | ||
Date | ||
_____________________ | ||
Governor |