Bill Title: Relating to requiring backup generation at certain wastewater treatment facilities.
Spectrum: Partisan Bill (Republican 1-0)
Status: (Introduced) 2025-02-28 - Referred to Business & Commerce [SB1290 Detail]
Download: Texas-2025-SB1290-Introduced.html
89R9777 DRS-D | ||
By: Schwertner | S.B. No. 1290 |
|
||
|
||
relating to requiring backup generation at certain wastewater | ||
treatment facilities. | ||
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | ||
SECTION 1. Subchapter B, Chapter 26, Water Code, is amended | ||
by adding Section 26.054 to read as follows: | ||
Sec. 26.054. STANDARDS OF EMERGENCY OPERATIONS FOR PACKAGE | ||
PLANT. (a) In this section: | ||
(1) "Emergency operations" means the operation of a | ||
package plant during an extended power outage that impacts the | ||
package plant. | ||
(2) "Extended power outage" means a power outage | ||
lasting for more than 24 hours. | ||
(3) "Package plant" means a pre-manufactured | ||
wastewater treatment facility with a capacity of less than 500,000 | ||
gallons per day. The term includes an extended aeration plant, | ||
sequencing batch reactor, or oxidation ditch. | ||
(b) The operator of a package plant shall: | ||
(1) ensure the emergency operation of the package | ||
plant during an extended power outage as soon as safe and | ||
practicable following the occurrence of a natural disaster; and | ||
(2) adopt and submit to the commission for its | ||
approval: | ||
(A) an emergency preparedness plan that | ||
demonstrates the operator's ability to provide the emergency | ||
operations described by Subdivision (1); and | ||
(B) a timeline for implementing the plan | ||
described by Paragraph (A). | ||
(c) The commission shall review an emergency preparedness | ||
plan submitted under Subsection (b). If the commission determines | ||
that the plan is not acceptable, the commission shall recommend | ||
changes to the plan. The commission must make its recommendations | ||
on or before the 90th day after the date the commission receives the | ||
plan. In accordance with commission rules, an emergency | ||
preparedness plan for a package plant shall provide for one or more | ||
of the following: | ||
(1) the maintenance of automatically starting | ||
auxiliary generators; | ||
(2) the sharing of auxiliary generator capacity with | ||
one or more operators of wastewater treatment facilities affected | ||
by an extended power outage, including through participation in a | ||
statewide mutual aid program; | ||
(3) the negotiation of leasing and contracting | ||
agreements, including emergency mutual aid agreements with other | ||
operators of wastewater treatment facilities, if the agreements | ||
provide for coordination with the division of emergency management | ||
in the governor's office; | ||
(4) the use of portable generators capable of serving | ||
multiple facilities equipped with quick-connect systems; | ||
(5) the use of on-site electrical generation or | ||
distributed generation facilities; | ||
(6) hardening the electric transmission and | ||
distribution system serving the package plant; | ||
(7) emergency wastewater treatment service capacity | ||
rules to maintain emergency operations; or | ||
(8) any other alternative determined by the commission | ||
to be acceptable. | ||
(d) Each operator of a package plant shall include in the | ||
package plant's emergency preparedness plan under Subsection (b) | ||
provisions for demonstrating the capability of the package plant to | ||
provide wastewater treatment service to its customers during | ||
emergencies. This subsection does not apply to wastewater | ||
treatment services that are unnecessary or otherwise subject to | ||
interruption or curtailment during emergencies under a contract. | ||
(e) The commission shall adopt rules to implement this | ||
section. | ||
(f) The commission shall provide an operator of a package | ||
plant with access to the commission's financial, managerial, and | ||
technical contractors to assist the operator in complying with the | ||
applicable emergency preparedness plan submission deadline. | ||
(g) The commission by rule shall create an emergency | ||
preparedness plan template for use by an operator of a package plant | ||
when submitting a plan under this section. The emergency | ||
preparedness plan template shall contain: | ||
(1) a list and explanation of the preparations an | ||
operator of a package plant may make under Subsection (c) for the | ||
commission to approve the package plant's emergency preparedness | ||
plan; and | ||
(2) a list of all commission rules and standards | ||
pertaining to emergency preparedness plans. | ||
(h) An emergency generator used as part of an approved | ||
emergency preparedness plan under Subsection (c) must be operated | ||
and maintained according to the manufacturer's specifications. | ||
(i) The commission shall inspect each package plant to | ||
ensure that the operator of the package plant complies with the | ||
approved plan. | ||
(j) The commission shall consider whether compliance with | ||
this section will cause a significant financial burden on customers | ||
of an operator of a package plant. | ||
(k) An operator of a package plant may adopt and enforce | ||
limitations on wastewater treatment service while the package plant | ||
is providing emergency operations. | ||
(l) Except as specifically required by this section, | ||
information provided by an operator of a package plant under this | ||
section is confidential and is not subject to disclosure under | ||
Chapter 552, Government Code. | ||
(m) The commission shall coordinate with the Public Utility | ||
Commission of Texas in the administration of this section. | ||
SECTION 2. (a) Not later than January 1, 2026, the Texas | ||
Commission on Environmental Quality shall adopt rules necessary to | ||
implement Section 26.054, Water Code, as added by this Act. | ||
(b) Not later than May 1, 2026, each operator of a package | ||
plant shall submit to the Texas Commission on Environmental Quality | ||
the emergency preparedness plan required by Section 26.054, Water | ||
Code, as added by this Act. | ||
(c) Not later than September 1, 2026, or upon final approval | ||
by the Texas Commission on Environmental Quality, each operator of | ||
a package plant shall implement the emergency preparedness plan | ||
required by Section 26.054, Water Code, as added by this Act. | ||
SECTION 3. This Act takes effect September 1, 2025. |