By: Sparks | S.B. No. 715 |
|
||
|
||
relating to the applicability of certain generation reliability | ||
requirements. | ||
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | ||
SECTION 1. Section 39.1592(a), Utilities Code, is amended | ||
to read as follows: | ||
(a) This section applies only to an electric generation | ||
facility in the ERCOT power region that is subject to [ |
||
standard generator interconnection agreement, [ |
||
year, and [ |
||
SECTION 2. (a) Sections 52(b) and (c), Chapter 410 (H.B. | ||
1500), Acts of the 88th Legislature, Regular Session, 2023, are | ||
repealed. | ||
(b) Notwithstanding the deadline provided by Section | ||
39.1592(b), Utilities Code, an owner or operator of an electric | ||
generation facility to which Section 39.1592(b), Utilities Code, | ||
applies shall make the first demonstration required by Section | ||
39.1592(b), Utilities Code, not later than January 1, 2027. | ||
SECTION 3. This Act takes effect September 1, 2025. |