By: Hall | S.B. No. 826 |
|
||
|
||
relating to the requirements for request for proposals for | ||
design-build contracts for highway projects. | ||
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | ||
SECTION 1. Sections 223.246(a) and (b), Transportation | ||
Code, are amended to read as follows: | ||
(a) The department shall issue a request for proposals to | ||
proposers short-listed under Section 223.245. A request for | ||
proposals must include: | ||
(1) information on the overall project goals; | ||
(2) publicly available cost estimates for the | ||
design-build portion of the project; | ||
(3) materials specifications; | ||
(4) special material requirements; | ||
(5) [ |
||
|
||
[ |
||
not required to undertake an effort to locate utilities; | ||
(6) [ |
||
requirements; | ||
(7) [ |
||
(8) [ |
||
department relating to awarding contracts to disadvantaged | ||
business enterprises or small business enterprises; | ||
(9) [ |
||
information related to the project; | ||
(10) [ |
||
the project; | ||
(11) [ |
||
technical proposal required under Subsection (d), including a | ||
description of the form and level of completeness of drawings | ||
expected; | ||
(12) [ |
||
and cost proposals required under Subsection (d) and the formula by | ||
which the proposals will be evaluated and ranked; and | ||
(13) [ |
||
technical proposals, and the relative weighting of those criteria. | ||
(b) The formula used to evaluate proposals under Subsection | ||
(a)(12) [ |
||
weighting to the cost proposal. | ||
SECTION 2. Section 370.406(a), Transportation Code, is | ||
amended to read as follows: | ||
(a) An authority shall issue a request for detailed | ||
proposals to proposers qualified or short-listed under Section | ||
370.405. A request for detailed proposals must include: | ||
(1) information on the overall project goals; | ||
(2) the authority's cost estimates for the | ||
design-build portion of the work; | ||
(3) materials specifications; | ||
(4) special material requirements; | ||
(5) [ |
||
|
||
[ |
||
not required to undertake an effort to locate utilities; | ||
(6) [ |
||
requirements; | ||
(7) [ |
||
(8) [ |
||
authority pursuant to Section 370.183 relating to awarding | ||
contracts to disadvantaged businesses; | ||
(9) [ |
||
information related to the project; | ||
(10) [ |
||
the project; | ||
(11) [ |
||
technical proposal required under Subsection (c), including a | ||
description of the form and level of completeness of drawings | ||
expected; | ||
(12) [ |
||
and cost proposals required under Subsection (c) and the formula by | ||
which the proposals will be evaluated and ranked, provided that the | ||
formula shall allocate at least 70 percent of the weighting to the | ||
cost proposal; and | ||
(13) [ |
||
element of the technical proposal. | ||
SECTION 3. The change in law made by this Act applies only | ||
to a contract entered into on or after the effective date of this | ||
Act. A contract entered into before the effective date of this Act | ||
is governed by the law in effect when the contract was entered into, | ||
and the former law is continued in effect for that purpose. | ||
SECTION 4. This Act takes effect August 31, 2015. |