Bill Text: HI HB2525 | 2012 | Regular Session | Amended
Bill Title: Electric Reliability Standards; Interconnection Requirements; Grid Interconnection; Hawaii Electricity Reliability Administrator; Hawaii Electricity Reliability Surcharge
Spectrum: Partisan Bill (Democrat 1-0)
Status: (Introduced - Dead) 2012-02-15 - (H) Report adopted. referred to the committee(s) on FIN as amended in HD 2 with none voting aye with reservations; none voting no (0) and Belatti, C. Lee, M. Lee, Tokioka excused (4). [HB2525 Detail]
Download: Hawaii-2012-HB2525-Amended.html
STAND. COM. REP. NO. 398-12
Honolulu, Hawaii
, 2012
RE: H.B. No. 2525
H.D. 2
Honorable Calvin K.Y. Say
Speaker, House of Representatives
Twenty-Sixth State Legislature
Regular Session of 2012
State of Hawaii
Sir:
Your Committee on Consumer Protection & Commerce, to which was referred H.B. No. 2525, H.D. 1, entitled:
"A BILL FOR AN ACT RELATING TO ELECTRICITY,"
begs leave to report as follows:
access and interconnection issues. Furthermore, the measure allows the PUC to contract with an entity, designated as the Hawaii Electricity Reliability Administrator, to perform critical-reliability and grid-oversight functions.
The Office of the Governor, Department of Business, Economic Development, and Tourism, Solar Energy Industries Association, Sierra Club – Hawaii Chapter, Blue Planet Foundation, ILWU Local 142, Hawaii Solar Energy Association, and Life of the Land supported this bill. Hawaiian Electric Company, Maui Electric Company, and Hawaii Electric Light Company supported the intent of this measure. The PUC submitted comments.
After careful consideration, your Committee has amended this bill by, among other things:
(1) Re-defining "ancillary services";
(2) Clarifying the role of the Hawaii Electricity Reliability Administrator (HERA) in enforcing and ensuring compliance with the electric-reliability law;
(3) Expanding the kinds of appropriate and reasonable costs recoverable by a utility under the Hawaii Electricity Reliability Surcharge to include interconnection studies and other analyses associated with studying the impact of necessary infrastructure and operational requirements needed to reliably interconnect a generator;
(4) Specifying that the HERA contracted for by the PUC must satisfy the qualification requirements established by the PUC;
(5) Making conforming amendments; and
(6) Making technical, nonsubstantive amendments for purposes of clarity, consistency, and style.
As affirmed by the record of votes of the members of your Committee on Consumer Protection & Commerce that is attached to this report, your Committee is in accord with the intent and purpose of H.B. No. 2525, H.D. 1, as amended herein, and recommends that it be referred to the Committee on Finance in the form attached hereto as H.B. No. 2525, H.D. 2.
Respectfully submitted on behalf of the members of the Committee on Consumer Protection & Commerce,
|
|
____________________________ ROBERT N. HERKES, Chair |
|
|
|