Bill Title: Amends the Environmental Protection Act. Sets the fee for NPDES construction site storm water permits at $500. Prohibits the imposition of a NPDES construction site storm water permit fee on any person for storm water discharges from a construction site that is smaller than 5 acres. Effective July 1, 2009.
Spectrum: Partisan Bill (Democrat 1-0)
Status: (Passed) 2009-08-11 - Public Act . . . . . . . . . 96-0245 [HB0629 Detail]
Download: Illinois-2009-HB0629-Introduced.html
Bill Title: Amends the Environmental Protection Act. Sets the fee for NPDES construction site storm water permits at $500. Prohibits the imposition of a NPDES construction site storm water permit fee on any person for storm water discharges from a construction site that is smaller than 5 acres. Effective July 1, 2009.
Spectrum: Partisan Bill (Democrat 1-0)
Status: (Passed) 2009-08-11 - Public Act . . . . . . . . . 96-0245 [HB0629 Detail]
Download: Illinois-2009-HB0629-Introduced.html
|
|||||||||||||||||||||||||
|
|||||||||||||||||||||||||
| |||||||||||||||||||||||||
| |||||||||||||||||||||||||
| |||||||||||||||||||||||||
1 | AN ACT concerning safety.
| ||||||||||||||||||||||||
2 | Be it enacted by the People of the State of Illinois,
| ||||||||||||||||||||||||
3 | represented in the General Assembly:
| ||||||||||||||||||||||||
4 | Section 5. The Environmental Protection Act is amended by | ||||||||||||||||||||||||
5 | changing Section 12.5 as follows:
| ||||||||||||||||||||||||
6 | (415 ILCS 5/12.5)
| ||||||||||||||||||||||||
7 | Sec. 12.5. NPDES discharge fees; sludge permit fees.
| ||||||||||||||||||||||||
8 | (a) Beginning July 1, 2003, the Agency shall assess and | ||||||||||||||||||||||||
9 | collect annual fees
(i) in the amounts set forth in subsection | ||||||||||||||||||||||||
10 | (e) for all discharges that require
an NPDES permit under | ||||||||||||||||||||||||
11 | subsection (f) of Section 12, from each person holding an
NPDES | ||||||||||||||||||||||||
12 | permit authorizing those discharges (including a person who | ||||||||||||||||||||||||
13 | continues to
discharge under an expired permit pending | ||||||||||||||||||||||||
14 | renewal), and (ii) in the amounts
set forth in subsection (f) | ||||||||||||||||||||||||
15 | of this Section for all activities that require a
permit under | ||||||||||||||||||||||||
16 | subsection (b) of Section 12, from each person holding a | ||||||||||||||||||||||||
17 | domestic
sewage sludge generator or user permit.
| ||||||||||||||||||||||||
18 | Each person subject to this Section must remit the | ||||||||||||||||||||||||
19 | applicable annual fee to
the Agency in accordance with the | ||||||||||||||||||||||||
20 | requirements set forth in this Section and
any rules adopted | ||||||||||||||||||||||||
21 | pursuant to this Section.
| ||||||||||||||||||||||||
22 | (b) Within 30 days after the effective date of this | ||||||||||||||||||||||||
23 | Section, and each year thereafter, the Agency shall send a fee |
| |||||||
| |||||||
1 | notice by mail
to each existing permittee subject to a fee | ||||||
2 | under this Section at his or her
address of record. The notice | ||||||
3 | shall state the amount of the applicable annual
fee and the | ||||||
4 | date by which payment is required.
| ||||||
5 | Except as provided in subsection (c) with respect to | ||||||
6 | initial fees under
new permits and certain modifications of | ||||||
7 | existing permits, fees payable under
this Section are due by | ||||||
8 | the date
specified in the fee notice, which shall be no less | ||||||
9 | than 30 days after the date
the fee notice is mailed by the | ||||||
10 | Agency.
| ||||||
11 | (c) The initial annual fee for discharges under a new NPDES
| ||||||
12 | permit or for activity under a new
sludge generator or sludge | ||||||
13 | user
permit must be remitted to the Agency prior to the | ||||||
14 | issuance of the permit.
The Agency shall provide notice of the | ||||||
15 | amount of the fee to the applicant
during its review of the | ||||||
16 | application. In the case of a new
NPDES
or sludge permit issued | ||||||
17 | during the months of January through June, the Agency
may | ||||||
18 | prorate the initial annual fee payable under this Section.
| ||||||
19 | The initial annual fee for discharges or other activity | ||||||
20 | under a general
NPDES permit must be remitted to the Agency as | ||||||
21 | part of the application
for coverage under that general permit.
| ||||||
22 | In the case of construction site stormwater discharges for | ||||||
23 | which a new NPDES permit is issued during the months of January | ||||||
24 | through June, no annual fee shall be due for the 12 months | ||||||
25 | beginning July 1 that immediately follow the period for which | ||||||
26 | the initial annual fee was due.
|
| |||||||
| |||||||
1 | If a requested modification to an existing NPDES permit | ||||||
2 | causes a change in
the applicable fee categories under | ||||||
3 | subsection (e) that results in an increase
in the required fee, | ||||||
4 | the permittee must pay to the Agency the amount of the
| ||||||
5 | increase, prorated for the number of months remaining before | ||||||
6 | the next July 1,
before the modification is granted.
| ||||||
7 | (d) Failure to submit the fee required under this Section | ||||||
8 | by the due
date constitutes a violation of this Section. Late | ||||||
9 | payments shall incur an
interest penalty, calculated at the | ||||||
10 | rate in effect from time to time for tax
delinquencies under | ||||||
11 | subsection (a) of Section 1003 of the Illinois Income Tax
Act, | ||||||
12 | from the date the fee is due until the date the fee payment is | ||||||
13 | received
by the Agency.
| ||||||
14 | (e) The annual fees applicable to discharges under NPDES | ||||||
15 | permits are as
follows:
| ||||||
16 | (1) For NPDES permits for publicly owned treatment | ||||||
17 | works, other
facilities for which the wastewater being | ||||||
18 | treated and discharged is primarily
domestic sewage, and | ||||||
19 | wastewater discharges from the operation of public water
| ||||||
20 | supply treatment facilities, the fee is:
| ||||||
21 | (i) $1,500 for the 12 months beginning July 1, 2003 | ||||||
22 | and $500 for each subsequent year, for facilities with | ||||||
23 | a Design Average Flow rate of less than
100,000 gallons | ||||||
24 | per day;
| ||||||
25 | (ii) $5,000 for the 12 months beginning July 1, | ||||||
26 | 2003 and $2,500 for each subsequent year, for |
| |||||||
| |||||||
1 | facilities with a Design Average Flow rate of at least
| ||||||
2 | 100,000 gallons per day but less than 500,000 gallons | ||||||
3 | per day;
| ||||||
4 | (iii) $7,500 for facilities with a Design Average | ||||||
5 | Flow rate of at least
500,000 gallons per day but less | ||||||
6 | than 1,000,000 gallons per day;
| ||||||
7 | (iv) $15,000 for facilities with a Design Average | ||||||
8 | Flow rate of at least
1,000,000 gallons per day but | ||||||
9 | less than 5,000,000 gallons per day;
| ||||||
10 | (v) $30,000 for facilities with a Design Average | ||||||
11 | Flow rate of at least
5,000,000 gallons per day but | ||||||
12 | less than 10,000,000 gallons per day; and
| ||||||
13 | (vi) $50,000 for facilities with a Design Average | ||||||
14 | Flow rate of
10,000,000 gallons per day or more.
| ||||||
15 | (2) For NPDES permits for treatment works or sewer | ||||||
16 | collection systems
that include combined sewer overflow | ||||||
17 | outfalls, the fee is:
| ||||||
18 | (i) $1,000 for systems serving a tributary | ||||||
19 | population of 10,000 or less;
| ||||||
20 | (ii) $5,000 for systems serving a tributary | ||||||
21 | population that is greater
than 10,000 but not more | ||||||
22 | than 25,000; and
| ||||||
23 | (iii) $20,000 for systems serving a tributary | ||||||
24 | population that is greater
than 25,000.
| ||||||
25 | The fee amounts in this subdivision (e)(2) are in | ||||||
26 | addition to the fees
stated in subdivision (e)(1) when the |
| |||||||
| |||||||
1 | combined sewer overflow outfall is
contained within a | ||||||
2 | permit subject to subsection (e)(1) fees.
| ||||||
3 | (3) For NPDES permits for mines producing coal, the fee | ||||||
4 | is $5,000.
| ||||||
5 | (4) For NPDES permits for mines other than mines | ||||||
6 | producing coal, the fee
is $5,000.
| ||||||
7 | (5) For NPDES permits for industrial activity where | ||||||
8 | toxic substances are
not regulated, other than permits | ||||||
9 | covered under subdivision (e)(3) or (e)(4),
the fee is:
| ||||||
10 | (i) $1,000 for a facility with a Design Average | ||||||
11 | Flow rate that is not
more than 10,000 gallons per day;
| ||||||
12 | (ii) $2,500 for a facility with a Design Average | ||||||
13 | Flow rate that is more
than 10,000 gallons per day but | ||||||
14 | not more than 100,000 gallons per day; and
| ||||||
15 | (iii) $10,000 for a facility with a Design Average | ||||||
16 | Flow rate that is
more than 100,000 gallons per day.
| ||||||
17 | (6) For NPDES permits for industrial activity where | ||||||
18 | toxic substances are
regulated, other than permits covered | ||||||
19 | under subdivision (e)(3) or (e)(4), the
fee is:
| ||||||
20 | (i) $15,000 for a facility with a Design Average | ||||||
21 | Flow rate that is not
more than 250,000 gallons per | ||||||
22 | day; and
| ||||||
23 | (ii) $20,000 for a facility with a Design Average | ||||||
24 | Flow rate that is
more than 250,000 gallons per day.
| ||||||
25 | (7) For NPDES permits for industrial activity | ||||||
26 | classified by USEPA as a
major discharge, other than |
| |||||||
| |||||||
1 | permits covered under subdivision (e)(3) or (e)(4),
the fee | ||||||
2 | is:
| ||||||
3 | (i) $30,000 for a facility where toxic substances | ||||||
4 | are not regulated; and
| ||||||
5 | (ii) $50,000 for a facility where toxic substances | ||||||
6 | are regulated.
| ||||||
7 | (8) For NPDES permits for municipal separate storm | ||||||
8 | sewer systems, the fee
is $1,000.
| ||||||
9 | (9) For NPDES permits for construction site or | ||||||
10 | industrial storm water,
the fee is $500 | ||||||
11 | (10) For NPDES permits for construction site storm | ||||||
12 | water, the fee is $500. However, a fee under subsection | ||||||
13 | (e)(10) of this Section must not be imposed on any person | ||||||
14 | for storm water discharges from a construction site that is | ||||||
15 | smaller than 5 acres .
| ||||||
16 | (f) The annual fee for activities under a permit that | ||||||
17 | authorizes applying
sludge on land is $2,500 for a sludge | ||||||
18 | generator permit and $5,000 for a sludge
user permit.
| ||||||
19 | (g) More than one of the annual fees specified in | ||||||
20 | subsections (e) and (f)
may be applicable to a permit holder. | ||||||
21 | These fees are in addition to any other
fees required under | ||||||
22 | this Act.
| ||||||
23 | (h) The fees imposed under this Section do not apply to the | ||||||
24 | State or any
department or agency of the State, nor to any | ||||||
25 | school district, or to any private sewage disposal system as | ||||||
26 | defined in the Private Sewage Disposal Licensing Act (225 ILCS |
| |||||||
| |||||||
1 | 225/).
| ||||||
2 | (i) The Agency may adopt rules to administer the fee | ||||||
3 | program established
in this Section. The Agency may include | ||||||
4 | provisions pertaining to invoices,
notice of late payment, | ||||||
5 | refunds, and disputes concerning the amount or timeliness of
| ||||||
6 | payment. The Agency may set forth procedures and criteria for | ||||||
7 | the acceptance
of payments. The absence of such rules does not | ||||||
8 | affect the duty of the Agency
to immediately begin the | ||||||
9 | assessment and collection of fees under this Section.
| ||||||
10 | (j) All fees and interest penalties collected by the Agency | ||||||
11 | under this
Section shall be deposited into the Illinois Clean | ||||||
12 | Water Fund, which is
hereby created as a special fund in the | ||||||
13 | State treasury. Gifts,
supplemental environmental project | ||||||
14 | funds, and grants may be deposited into
the Fund. Investment | ||||||
15 | earnings on moneys held in the Fund shall be credited
to the | ||||||
16 | Fund.
| ||||||
17 | Subject to appropriation, the moneys in the Fund shall be | ||||||
18 | used by the
Agency to carry out the Agency's clean water | ||||||
19 | activities.
| ||||||
20 | (k) Except as provided in subsection (l) or Agency rules, | ||||||
21 | fees paid to the Agency under this Section are not refundable.
| ||||||
22 | (l) The Agency may refund the difference between (a) the | ||||||
23 | amount paid by any person under subsection (e)(1)(i) or | ||||||
24 | (e)(1)(ii) of this Section for the 12 months beginning July 1, | ||||||
25 | 2004 and (b) the amount due under subsection (e)(1)(i) or | ||||||
26 | (e)(1)(ii) as established by this amendatory Act of the 93rd |
| |||||||
| |||||||
1 | General Assembly.
| ||||||
2 | (Source: P.A. 95-516, eff. 8-28-07.)
| ||||||
3 | Section 99. Effective date. This Act takes effect July 1, | ||||||
4 | 2009.
|