Bill Text: IL SB2860 | 2023-2024 | 103rd General Assembly | Introduced
Bill Title: Amends the Carbon Dioxide Transportation and Sequestration Act. Provides that a certificate of authority does not grant an owner or operator of a carbon dioxide pipeline the authority to take and acquire an easement in any property or interest in property for the construction, maintenance, or operation of a carbon dioxide pipeline through the exercise of the power of eminent domain. Removes corresponding provisions concerning eminent domain. Repeals a provision that provides procedures for acquiring easements.
Spectrum: Slight Partisan Bill (Republican 2-1)
Status: (Introduced) 2024-03-15 - Rule 3-9(a) / Re-referred to Assignments [SB2860 Detail]
Download: Illinois-2023-SB2860-Introduced.html
| ||||||||||||||||||||||
| ||||||||||||||||||||||
| ||||||||||||||||||||||
1 | AN ACT concerning regulation.
| |||||||||||||||||||||
2 | Be it enacted by the People of the State of Illinois, | |||||||||||||||||||||
3 | represented in the General Assembly:
| |||||||||||||||||||||
4 | Section 5. The Carbon Dioxide Transportation and | |||||||||||||||||||||
5 | Sequestration Act is amended by changing Section 20 as | |||||||||||||||||||||
6 | follows:
| |||||||||||||||||||||
7 | (220 ILCS 75/20) | |||||||||||||||||||||
8 | Sec. 20. Application. | |||||||||||||||||||||
9 | (a) No person or entity may construct, operate, or repair | |||||||||||||||||||||
10 | a carbon dioxide pipeline unless the person or entity | |||||||||||||||||||||
11 | possesses a certificate of authority. | |||||||||||||||||||||
12 | (b) The Commission, after a hearing, may grant an | |||||||||||||||||||||
13 | application for a certificate of authority authorizing the | |||||||||||||||||||||
14 | construction and operation of a carbon dioxide pipeline if it | |||||||||||||||||||||
15 | makes a specific written finding as to each of the following: | |||||||||||||||||||||
16 | (1) the application was properly filed; | |||||||||||||||||||||
17 | (2) the applicant is fit, willing, and able to | |||||||||||||||||||||
18 | construct and operate the pipeline in compliance with this | |||||||||||||||||||||
19 | Act and with Commission regulations and orders of the | |||||||||||||||||||||
20 | Commission or any applicable federal agencies; | |||||||||||||||||||||
21 | (3) the applicant has entered into an agreement with a | |||||||||||||||||||||
22 | clean coal facility, a clean coal SNG facility, or any | |||||||||||||||||||||
23 | other source that will result in the reduction of carbon |
| |||||||
| |||||||
1 | dioxide emissions from that source; | ||||||
2 | (4) the applicant has filed with the Pipeline and | ||||||
3 | Hazardous Materials Safety Administration of the U.S. | ||||||
4 | Department of Transportation all forms required by that | ||||||
5 | agency in advance of constructing a carbon dioxide | ||||||
6 | pipeline; | ||||||
7 | (5) the applicant has filed with the U.S. Army Corps | ||||||
8 | of Engineers all applications for permits required by that | ||||||
9 | agency in advance of constructing a carbon dioxide | ||||||
10 | pipeline; | ||||||
11 | (6) the applicant has entered into an agreement with | ||||||
12 | the Illinois Department of Agriculture that governs the | ||||||
13 | mitigation of agricultural impacts associated with the | ||||||
14 | construction of the proposed pipeline; | ||||||
15 | (7) the applicant possesses the financial, managerial, | ||||||
16 | legal, and technical qualifications necessary to construct | ||||||
17 | and operate the proposed carbon dioxide pipeline; and | ||||||
18 | (8) the proposed pipeline is consistent with the | ||||||
19 | public interest, public benefit, and legislative purpose | ||||||
20 | as set forth in this Act. In addition to any other evidence | ||||||
21 | the Commission may consider on this specific finding, the | ||||||
22 | Commission shall consider the following: | ||||||
23 | (A) any evidence of the effect of the pipeline | ||||||
24 | upon the economy, infrastructure, and public safety | ||||||
25 | presented by local governmental units that will be | ||||||
26 | affected by the proposed pipeline route; |
| |||||||
| |||||||
1 | (B) any evidence of the effect of the pipeline | ||||||
2 | upon property values presented by property owners who | ||||||
3 | will be affected by the proposed pipeline or facility , | ||||||
4 | provided that the Commission need not hear evidence as | ||||||
5 | to the actual valuation of property such as that as | ||||||
6 | would be presented to and determined by the courts | ||||||
7 | under the Eminent Domain Act ; | ||||||
8 | (C) any evidence presented by the Department of | ||||||
9 | Commerce and Economic Opportunity regarding the | ||||||
10 | current and future local, State-wide, or regional | ||||||
11 | economic effect, direct or indirect, of the proposed | ||||||
12 | pipeline or facility including, but not limited to, | ||||||
13 | ability of the State to attract economic growth, meet | ||||||
14 | future energy requirements, and ensure compliance with | ||||||
15 | environmental requirements and goals; | ||||||
16 | (D) any evidence addressing the factors described | ||||||
17 | in items (1) through (8) of this subsection (b) or | ||||||
18 | other relevant factors that is presented by any other | ||||||
19 | State agency, the applicant, a party, or other entity | ||||||
20 | that participates in the proceeding, including | ||||||
21 | evidence presented by the Commission's staff; and | ||||||
22 | (E) any evidence presented by any State or federal | ||||||
23 | governmental entity as to how the proposed pipeline | ||||||
24 | will affect the security, stability, and reliability | ||||||
25 | of energy. | ||||||
26 | In its written order, the Commission shall address all of |
| |||||||
| |||||||
1 | the evidence presented, and if the order is contrary to any of | ||||||
2 | the evidence, the Commission shall state the reasons for its | ||||||
3 | determination with regard to that evidence. | ||||||
4 | (c) When an applicant files its application for a | ||||||
5 | certificate of authority with the Commission, it shall provide | ||||||
6 | notice to each local government where the proposed pipeline | ||||||
7 | will be located and include a map of the proposed pipeline | ||||||
8 | route. The applicant shall also publish notice in a newspaper | ||||||
9 | of general circulation in each county where the proposed | ||||||
10 | pipeline is located. | ||||||
11 | (d) An application for a certificate of authority filed | ||||||
12 | pursuant to this Section shall request either that the | ||||||
13 | Commission review and approve a specific route for a carbon | ||||||
14 | dioxide pipeline, or that the Commission review and approve a | ||||||
15 | project route width that identifies the areas in which the | ||||||
16 | pipeline would be located, with such width ranging from the | ||||||
17 | minimum width required for a pipeline right-of-way up to 200 | ||||||
18 | feet in width. A map of the route or route width shall be | ||||||
19 | included in the application. The purpose for allowing the | ||||||
20 | option of review and approval of a project route width is to | ||||||
21 | provide increased flexibility during the construction process | ||||||
22 | to accommodate specific landowner requests, avoid | ||||||
23 | environmentally sensitive areas, or address special | ||||||
24 | environmental permitting requirements. | ||||||
25 | (e) The Commission's rules shall ensure that notice of an | ||||||
26 | application for a certificate of authority is provided within |
| |||||||
| |||||||
1 | 30 days after filing to the landowners along a proposed | ||||||
2 | project route, or to the potentially affected landowners | ||||||
3 | within a proposed project route width, using the notification | ||||||
4 | procedures set forth in the Commission's rules. If the | ||||||
5 | Commission grants approval of a project route width as opposed | ||||||
6 | to a specific project route, then the applicant must, as it | ||||||
7 | finalizes the actual pipeline alignment within the project | ||||||
8 | route width, file its final list of affected landowners with | ||||||
9 | the Commission at least 14 days in advance of beginning | ||||||
10 | construction on any tract within the project route width and | ||||||
11 | also provide the Commission with at least 14 days' notice | ||||||
12 | before filing a complaint for eminent domain in the circuit | ||||||
13 | court with regard to any tract within the project route width . | ||||||
14 | (f) The Commission shall make its determination on any | ||||||
15 | application for a certificate of authority filed pursuant to | ||||||
16 | this Section and issue its final order within 11 months after | ||||||
17 | the date that the application is filed. The Commission's | ||||||
18 | failure to act within this time period shall not be deemed an | ||||||
19 | approval or denial of the application. | ||||||
20 | (g) A final order of the Commission granting a certificate | ||||||
21 | of authority pursuant to this Act shall be conditioned upon | ||||||
22 | the applicant obtaining all required permits or approvals from | ||||||
23 | the Pipeline and Hazardous Materials Safety Administration of | ||||||
24 | the U.S. Department of Transportation, U.S. Army Corps of | ||||||
25 | Engineers, and Illinois Department of Agriculture, in addition | ||||||
26 | to all other permits and approvals necessary for the |
| |||||||
| |||||||
1 | construction and operation of the pipeline prior to the start | ||||||
2 | of any construction. The final order must specifically | ||||||
3 | prohibit the start of any construction until all such permits | ||||||
4 | and approvals have been obtained. | ||||||
5 | (h) Within 6 months after the Commission's entry of an | ||||||
6 | order approving either a specific route or a project route | ||||||
7 | width under this Section, the owner or operator of the carbon | ||||||
8 | dioxide pipeline that receives that order may file | ||||||
9 | supplemental applications for minor route deviations outside | ||||||
10 | the approved project route width, allowing for additions or | ||||||
11 | changes to the approved route to address environmental | ||||||
12 | concerns encountered during construction or to accommodate | ||||||
13 | landowner requests. The supplemental application shall | ||||||
14 | specifically detail the environmental concerns or landowner | ||||||
15 | requests prompting the route changes, including the names of | ||||||
16 | any landowners or entities involved. Notice of a supplemental | ||||||
17 | application shall be provided to any State agency or unit of | ||||||
18 | local government that appeared in the original proceeding and | ||||||
19 | to any landowner affected by the proposed route deviation at | ||||||
20 | the time that supplemental application is filed. The route | ||||||
21 | deviations shall be approved by the Commission no sooner than | ||||||
22 | 90 days after all interested parties receive notice of the | ||||||
23 | supplemental application, unless a written objection is filed | ||||||
24 | to the supplemental application within 45 days after such | ||||||
25 | notice is received. If a written objection is filed, then the | ||||||
26 | Commission shall issue an order either granting or denying the |
| |||||||
| |||||||
1 | route deviation within 90 days after the filing of the | ||||||
2 | objection. Hearings on any such supplemental application shall | ||||||
3 | be limited to the reasonableness of the specific variance | ||||||
4 | proposed, and the issues of the public interest and benefit of | ||||||
5 | the project or fitness of the applicant shall be considered | ||||||
6 | only to the extent that the route deviation has raised new | ||||||
7 | concerns with regard to those issues. | ||||||
8 | (i) A certificate of authority to construct and operate a | ||||||
9 | carbon dioxide pipeline issued by the Commission shall contain | ||||||
10 | a grant of authority to construct and operate a carbon dioxide | ||||||
11 | pipeline as requested in the application, subject to the laws | ||||||
12 | of this State. A certificate of authority does not grant an | ||||||
13 | owner or operator of a carbon dioxide pipeline the authority | ||||||
14 | to take and acquire an easement in any property or interest in | ||||||
15 | property for the construction, maintenance, or operation of a | ||||||
16 | carbon dioxide pipeline through the exercise of the power of | ||||||
17 | eminent domain. and include all of the following: | ||||||
18 | (1) a grant of authority to construct and operate a | ||||||
19 | carbon dioxide pipeline as requested in the application, | ||||||
20 | subject to the laws of this State; and | ||||||
21 | (2) a limited grant of authority to take and acquire | ||||||
22 | an easement in any property or interest in property for | ||||||
23 | the construction, maintenance, or operation of a carbon | ||||||
24 | dioxide pipeline in the manner provided for the exercise | ||||||
25 | of the power of eminent domain under the Eminent Domain | ||||||
26 | Act. The limited grant of authority shall be restricted |
| |||||||
| |||||||
1 | to, and exercised solely for, the purpose of siting, | ||||||
2 | rights-of-way, and easements appurtenant, including | ||||||
3 | construction and maintenance. The applicant shall not | ||||||
4 | exercise this power until it has used reasonable and good | ||||||
5 | faith efforts to acquire the property or easement thereto. | ||||||
6 | The applicant may thereafter use this power when the | ||||||
7 | applicant determines that the easement is necessary to | ||||||
8 | avoid unreasonable delay or economic hardship to the | ||||||
9 | progress of activities carried out pursuant to the | ||||||
10 | certificate of authority. | ||||||
11 | (Source: P.A. 97-534, eff. 8-23-11.)
|