Bill Text: NJ S3308 | 2024-2025 | Regular Session | Amended


Bill Title: Requires electric public utilities to implement certain improvements to the interconnection process for certain grid supply solar facilities.

Spectrum: Partisan Bill (Democrat 2-0)

Status: (Introduced) 2024-06-28 - Senate Amendment (Voice) (Ruiz) [S3308 Detail]

Download: New_Jersey-2024-S3308-Amended.html

[First Reprint]

SENATE, No. 3308

STATE OF NEW JERSEY

221st LEGISLATURE

 

INTRODUCED MAY 20, 2024

 


 

Sponsored by:

Senator  NICHOLAS P. SCUTARI

District 22 (Somerset and Union)

Senator  LINDA R. GREENSTEIN

District 14 (Mercer and Middlesex)

 

 

 

 

SYNOPSIS

     Requires electric public utilities to implement certain improvements to the interconnection process for certain grid supply solar facilities.

 

CURRENT VERSION OF TEXT

     As amended by the Senate on June 28, 2024.

  


An Act concerning certain grid supply solar facilities and supplementing Title 48 of the Revised Statutes.

 

     Be It Enacted by the Senate and General Assembly of the State of New Jersey:

 

      1.  a.  As used in this section:

      "Board" means the Board of Public Utilities.

      "Class I renewable energy " means the same as the term is defined in section 3 of P.L.1999, c.23 (C.48:3-51).

      "Electric public utility" means the same as the term is defined in section 3 of P.L.1999, c.23 (C.48:3-51).

      "Electric transmission or distribution system" means the intrastate electric power grid, maintained by an applicable electric public utility in the State that is subject to the jurisdiction of the board.

      "Grid supply solar facility" means the same as the term is defined in section 3 of P.L.1999, c.23 (C.48:3-51).

      "Interconnection facilities" means dedicated electric facilities between a renewable energy generator or renewable energy generating facility and the electric transmission or distribution system, including any modification, additions, or upgrades that are necessary to physically and safely interconnect the renewable energy generator or renewable energy generating facility to the electric distribution or transmission system.  "Interconnection facilities" does not include electric distribution lines that are used to deliver electricity to end-use customers.

      "Level 3 interconnection application process" means the procedure, criteria, and protocols established for applications to connect renewable energy generation facilities to the transmission and distribution system that are greater than two megawatts in size, or that do not meet certain certification requirements, as developed by the board pursuant to P.L.1999, c.23 (C.48:3-49 et al.).

      "PJM Interconnection, L.L.C." or "PJM" means the same as the term is defined in section 3 of P.L.1999, c.23 (C.48:3-51).

      "Renewable energy certificate" or "REC" means the same as the term is defined in section 3 of P.L.1999, c.23 (C.48:3-51).

      "State incentives" means Class I RECs, SRECs, SREC-IIs, TRECs, or any other applicable State renewable energy certificate, credit, or incentive.

      "State incentive program" means any State incentive program whereby solar energy production facilities are eligible to receive state incentives.

      "Solar renewable energy certificate" or "SREC" means the same as the term is defined in section 3 of P.L.1999, c.23 (C.48:3-51).

      "Solar renewable energy certificate-II" or "SREC-II" means the same as the term is defined in section 3 of P.L.1999, c.23 (C.48:3-51).

      b.  Notwithstanding the provisions of P.L.1999, c.23 (C.48:3-49 et al.), P.L.2021, c.169 (C.48:3-114 et al.), or any other law, rule, regulation, or order to the contrary, each electric public utility shall accept, process, and approve any Level 3 interconnection application for interconnection to that electric public utility's electric distribution or transmission system for any grid supply solar facility with a capacity of 20 megawatts or less, measured in alternating current, unless the utility: (1) finds the application to be incomplete, based on application criteria and protocols developed by the utility; or (2) deems the interconnection to be unsafe or a risk to the stability 1, reliability, or power quality1 of the utility's electric distribution or transmission system.  If an electric public utility determines that the application is incomplete in accordance with (1) above, then the electric public utility, in response to the application, shall provide recommendations to the applicant as to how to modify the application to make it complete for review.  If, after receipt of a complete application, an electric public utility determines that the proposed interconnection is unsafe or a risk to the stability 1, reliability, or power quality1 of the utility's electric distribution or transmission system in accordance with (2) above, then the electric public utility, in response to the application, shall provide recommendations to the applicant as to how to reconfigure, adjust, downsize, or otherwise modify the proposed grid supply solar facility so that it is not unsafe or a risk to the stability 1, reliability, or power quality1 of the utility's electric distribution or transmission system and allow the applicant to resubmit following such modifications.

      c.  An electric public utility shall timely process any complete interconnection applications received pursuant to this section in accordance with the electric public utility's Level 3 interconnection application process and its applicable tariff.

      d.  A grid supply solar facility for which 1[a] an1 application is submitted pursuant to this section shall be permitted to interconnect to the electric public utility's transmission or distribution system in the State, provided that (1) the owner or developer of the grid supply solar facility complies with the electric public utility's applicable tariff and Level 3 interconnection application process, and (2) the owner or developer of the grid supply solar facility agrees to pay all required interconnection costs as identified by the electric public utility.

      e.  1[A grid supply solar facility that is connected to the electric transmission or distribution system pursuant to this section shall be compensated for the electricity supplied by the facility by the applicable electric public utility, on a real-time basis, based on the point of interconnection.

      f.]1  An electric public utility shall, upon application by the owner or operator of a grid supply solar facility, extend interconnection facilities, at the sole cost and expense of the applicant, to the applicable grid supply solar facility so that such facility may be connected to the electric distribution system 1, unless a board order issued after the effective date of this section modifies the interconnection cost allocation methodology, in which case the applicant shall abide by the modified methodology1 .  Any applicant for such an extension shall comply with the electric public utility's standard interconnection application process.  Any such interconnection facilities shall conform to applicable electric code construction standards, electric public utility construction standards, and any other applicable safety standards or code requirements.  Each electric public utility shall use commercially reasonable efforts to work collaboratively with solar energy generators to develop new construction standards where needed such that any line extensions do not adversely affect the safe and reliable operation of the electric distribution system.

      1[g.] f.1  A grid supply solar facility that is connected to the electric transmission or distribution system pursuant to this section shall be fully eligible for any applicable State incentives, provided that the facility obtains the board's approval for participation in the State incentive program.

     1[h.] g.1  No later than 120 days after the effective date of this act, the board shall adopt, pursuant to the "Administrative Procedure Act," P.L.1968, c.410 (C.52:14B-1 et seq.), rules and regulations as necessary for implementing the provisions of this section, which shall be based on existing rules located at N.J.A.C.14:3-8.1 et seq.

 

     2.    This act shall take effect immediately.

feedback