Bill Text: TX HB3211 | 2017-2018 | 85th Legislature | Introduced
Bill Title: Relating to requirements for the notice that excavators must provide to notification centers and underground facility operators for certain excavation operations.
Spectrum: Partisan Bill (Republican 1-0)
Status: (Introduced - Dead) 2017-03-30 - Referred to Energy Resources [HB3211 Detail]
Download: Texas-2017-HB3211-Introduced.html
85R12339 JXC-F | ||
By: Paddie | H.B. No. 3211 |
|
||
|
||
relating to requirements for the notice that excavators must | ||
provide to notification centers and underground facility operators | ||
for certain excavation operations. | ||
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | ||
SECTION 1. Section 251.151(a), Utilities Code, is amended | ||
to read as follows: | ||
(a) Except as provided by Sections 251.155, [ |
||
and 251.1565, a person who intends to excavate shall notify a | ||
notification center not earlier than the 14th day before the date | ||
the excavation is to begin or later than the 48th hour before the | ||
time the excavation is to begin, excluding Saturdays, Sundays, and | ||
legal holidays. | ||
SECTION 2. Subchapter D, Chapter 251, Utilities Code, is | ||
amended by adding Section 251.1565 to read as follows: | ||
Sec. 251.1565. LARGE OPERATION EXCAVATION EXCEPTION. (a) | ||
For the purposes of this section, "large operation" means an | ||
excavation operation conducted in a contiguous geographical area | ||
that: | ||
(1) exceeds one linear mile; or | ||
(2) reasonably requires more than 90 days to complete. | ||
(b) For a planned large operation, the excavator shall: | ||
(1) notify a notification center of the operation and | ||
include in the notice: | ||
(A) the information described by Section | ||
251.152; and | ||
(B) an indication that the operation is a large | ||
operation; and | ||
(2) provide written notice of the operation to each | ||
operator that may have an underground facility in the vicinity of | ||
the operation. | ||
(c) The excavator may not begin the large operation until | ||
the excavator and each operator that is known to the excavator to | ||
have an underground facility in the vicinity of the operation have | ||
entered into an agreement to coordinate the marking of the | ||
operator's underground facilities in segments as the operation | ||
progresses in order to coordinate the marking of the facilities | ||
with excavation schedules. The excavator and each operator shall | ||
determine a mutually agreed on marking schedule based on the | ||
planned operation schedule. | ||
(d) Once an excavator establishes a marking schedule under | ||
Subsection (c) with each operator that has an underground facility | ||
in the vicinity of the operation, the marking and notification | ||
requirements of Sections 251.151, 251.154, and 251.157 do not apply | ||
to the large operation. | ||
(e) An excavator may treat any excavation operation as a | ||
large operation for the purposes of notifying an operator of a | ||
planned excavation operation and determining a marking schedule | ||
with the operator if the operator agrees. | ||
(f) The excavator shall notify each operator with which the | ||
excavator has agreed on a marking schedule under this section if: | ||
(1) the start time of the large operation changes; | ||
(2) the information provided to the notification | ||
center under Subsection (b) for the large operation changes; or | ||
(3) the operator's markings are no longer visible, are | ||
unclear, or are damaged. | ||
(g) The excavator shall notify each operator with which the | ||
excavator has agreed on a marking schedule under this section of the | ||
time excavation will begin in close proximity to the operator's | ||
facility at least 24 hours before that time. | ||
SECTION 3. Section 251.157(a), Utilities Code, is amended | ||
to read as follows: | ||
(a) Each Class A underground facility operator contacted by | ||
the notification system shall mark the approximate location of its | ||
underground facilities at or near the site of the proposed | ||
excavation if the operator believes that marking the location is | ||
necessary. The operator shall mark the location not later than: | ||
(1) the 48th hour after the time the excavator gives to | ||
the notification system notice of intent to excavate, excluding | ||
Saturdays, Sundays, and legal holidays; | ||
(2) 11:59 a.m. on the Tuesday following a Saturday | ||
notification unless the intervening Monday is a holiday; | ||
(3) 11:59 a.m. on the Wednesday following a Saturday | ||
notification if the intervening Monday is a holiday; [ |
||
(4) if the operator must use additional equipment or | ||
excavate the proposed excavation site to mark the approximate | ||
location of its underground facilities, 96 hours after 8:00 a.m. on | ||
the business day following the date the excavator gives the | ||
notification system notice of intent to excavate; or | ||
(5) a time agreed to by the operator and the excavator. | ||
SECTION 4. This Act takes effect September 1, 2017. |