Bill Text: IN SB0365 | 2013 | Regular Session | Engrossed
Bill Title: Utility facility relocation.
Spectrum: Slight Partisan Bill (Republican 2-1)
Status: (Passed) 2013-05-13 - Public Law 79 [SB0365 Detail]
Download: Indiana-2013-SB0365-Engrossed.html
Citations Affected: IC 36-9.
Synopsis: Utility facility relocation. Authorizes a unit of local
government to enter into an agreement with a utility concerning the
relocation of the utility's facilities for a major highway, street, or road
project undertaken by the local unit. Requires that the agreement must
include a date for relocation and conditions under which the utility is
excused from meeting the date, including a force majeure clause.
Specifies that a unit that is responsible for relocation costs shall pay the
costs in arrears in accordance with the procedures of the state board of
accounts.
Effective: July 1, 2013.
(HOUSE SPONSORS _ KOCH, BATTLES, DEVON, NIEZGODSKI)
January 8, 2013, read first time and referred to Committee on Utilities.
February 7, 2013, amended, reported favorably _ Do Pass.
February 11, 2013, read second time, ordered engrossed.
February 12, 2013, engrossed. Read third time, passed. Yeas 49, nays 0.
February 26, 2013, read first time and referred to Committee on Utilities and Energy.
March 7, 2013, amended, reported _ Do Pass.
PRINTING CODE. Amendments: Whenever an existing statute (or a section of the Indiana Constitution) is being amended, the text of the existing provision will appear in this style type, additions will appear in this style type, and deletions will appear in
Additions: Whenever a new statutory provision is being enacted (or a new constitutional provision adopted), the text of the new provision will appear in this style type. Also, the word NEW will appear in that style type in the introductory clause of each SECTION that adds a new provision to the Indiana Code or the Indiana Constitution.
Conflict reconciliation: Text in a statute in this style type or
A BILL FOR AN ACT to amend the Indiana Code concerning
utilities.
Chapter 42. Utility Relocations
Sec. 1. As used in this chapter, "cost of relocation" has the meaning set forth in IC 8-1-9-2(b).
Sec. 2. As used in this chapter, "facility" has the meaning set forth in IC 8-1-26-7.
Sec. 3. As used in this chapter, "improvement project" means a project undertaken by a unit that involves:
(1) a highway, street, or road that is under the jurisdiction of the unit; and
(2) the relocation of a facility.
Sec. 4. As used in this chapter, "major project" means an improvement project designated by a unit as a major project under section 6 of this chapter.
Sec. 5. As used in this chapter, "utility" means the owner of a
facility.
Sec. 6. (a) A unit may designate an improvement project as a
major project. The unit shall consider the scope, complexity, and
duration of the project in making the designation.
(b) Before undertaking a major project, a unit shall make a
reasonable effort to do the following:
(1) Identify each facility located in a public right of way
within the geographical limits of the major project by:
(A) investigating field conditions; and
(B) reviewing base map data that is:
(i) maintained and updated by the association (as defined
in IC 8-1-26-3) under IC 8-1-26-17(c); and
(ii) made available by the association to the unit.
(2) Notify each utility that owns a facility identified under
subdivision (1) of the major project and the need, if any, to
relocate the facility.
Sec. 7. A unit may enter into an agreement with a utility
described in section 6(b)(2) of this chapter concerning the
relocation of the facility. The agreement must include the
following:
(1) A date certain by which the utility agrees to relocate the
facility.
(2) Conditions under which the utility is excused from
relocating the facility by the date described in subdivision (1),
including the following:
(A) The facility relocation was affected by:
(i) significantly differing site conditions;
(ii) unexpected impacts of other utilities; or
(iii) a force majeure event.
(B) Severe weather, delays in acquiring a relocation area,
or other factors beyond the control of the utility.
(3) Conditions under which the unit must notify the utility of
cancellations, delays, or changes related to the major project.
Sec. 8. If, as part of an improvement project, a unit is
responsible for relocation costs, the unit shall pay the relocation
costs in arrears in accordance with accounting procedures
established by the state board of accounts.
Sec. 9. This chapter does not limit or alter the authority of the
Indiana utility regulatory commission under IC 8-1-2-101 to
review a unit's determination, or the rights and duties of affected
parties, with respect to use of a public right of way as set forth in
IC 8-1-2-101.