Bill Text: TX SB1478 | 2011-2012 | 82nd Legislature | Introduced
NOTE: There are more recent revisions of this legislation. Read Latest Draft
Bill Title: Relating to deadlines for the Railroad Commission of Texas to review certain applications for surface coal mining operation permits.
Spectrum: Partisan Bill (Republican 2-0)
Status: (Passed) 2011-05-27 - Effective immediately [SB1478 Detail]
Download: Texas-2011-SB1478-Introduced.html
Bill Title: Relating to deadlines for the Railroad Commission of Texas to review certain applications for surface coal mining operation permits.
Spectrum: Partisan Bill (Republican 2-0)
Status: (Passed) 2011-05-27 - Effective immediately [SB1478 Detail]
Download: Texas-2011-SB1478-Introduced.html
By: Hegar | S.B. No. 1478 | |
|
||
|
||
relating to permit review timelines of the surface mining and | ||
reclamation division of the Railroad Commission of Texas. | ||
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | ||
SECTION 1. PURPOSE. The purpose of this Act is to establish | ||
timelines for the review of applications for surface coal mining | ||
permits, renewals, and revisions. | ||
SECTION 2. Section 134.004, Natural Resources Code, is | ||
amended by adding the following: | ||
(22) "Director" means the director, Surface Mining and | ||
Reclamation Division, Railroad Commission of Texas, or the | ||
director's representative. | ||
SECTION 3. Subchapter F, Chapter 134, Natural Resources | ||
Code, is amended by adding Sections 134.135, 134.136, and 134.137 | ||
to read as follows: | ||
Sec. 134.135. ADMINISTRATIVE REVIEW PERIOD FOR NEW PERMITS, | ||
RENEWALS, AND SIGNIFICANT REVISIONS. | ||
(a) The director shall complete a review to assess the | ||
administrative completeness of any application submitted for a new | ||
surface coal mine permit or the renewal or revision of such a permit | ||
within one week of receipt of the application. | ||
(1) If the application is found to be incomplete, the | ||
letter will identify for the applicant the specific information | ||
that causes an incompleteness determination and, upon the | ||
applicant's submittal of the requested information, shall make a | ||
determination whether the application is administratively complete | ||
within one week of receipt of requested information. | ||
(2) If the application is found to be administratively | ||
complete, the application will be filed with the office of general | ||
counsel for processing in accordance with commission rules and | ||
Chapter 2001, Texas Government Code. | ||
Sec. 134.136. TECHNICAL REVIEW PERIOD FOR NEW PERMITS, | ||
RENEWALS, AND SIGNIFICANT REVISIONS. | ||
(a) Within 120 days of receipt of an administratively | ||
complete application for a new permit or significant permit | ||
revision (or within 60 days for a renewal application), the | ||
director shall file documentation of its technical analysis with | ||
the commission's office of general counsel and contact the | ||
applicant to schedule a meeting to discuss the technical analysis | ||
review findings. | ||
(1) If the applicant files a supplement to the | ||
application, the director will follow the procedure outlined in | ||
section 134.135(a) regarding administrative review and review the | ||
supplement and respond with an addendum to its technical analysis | ||
within 30 days of receiving an administratively complete | ||
supplement, unless a substantive revision to the proposed mining | ||
and operation plan is made to the application in the supplemental | ||
filing. | ||
(2) If a substantive revision is made in the | ||
applicant's supplemental filing, the review shall be completed | ||
within 60 days from receipt of an administratively complete | ||
supplement. | ||
(b) During this review time period the director will request | ||
that the hearings examiner assigned to the case from the office of | ||
general counsel review the public notice to ensure that no material | ||
change, requiring additional notice, has occurred with this | ||
supplemental filing to the application. | ||
Sec. 134.137. REVIEW OF NONSIGNIFICANT REVISIONS | ||
(a) Within 60 days of receipt of a complete application for | ||
a non-significant permit revision, the director shall issue a | ||
written response to the applicant either authorizing the requested | ||
permit revision or providing a list of deficiency comments with | ||
precise citations to applicable regulation sections. | ||
(b) Within 30 days of receiving an applicant's response to | ||
deficiency comments, the director shall issue a written response | ||
authorizing the requested permit revision or setting out additional | ||
deficiencies consistent with the process outlined in subsection (a) | ||
of this section. | ||
SECTION 4. EFFECTIVE DATE. This Act applies to | ||
applications submitted on or after June 1, 2011. The director of | ||
the railroad commission shall take all reasonable steps necessary | ||
to ensure that applications still pending on the effective date of | ||
this Act are processed within timeframes that are consistent with | ||
permit review timeframes set out in this Act. |