S.B. No. 1478 |
|
||
relating to deadlines for the Railroad Commission of Texas to | ||
review certain applications for surface coal mining operation | ||
permits. | ||
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS: | ||
SECTION 1. Section 134.004, Natural Resources Code, is | ||
amended by adding Subdivision (7-a) to read as follows: | ||
(7-a) "Director" means the director, Surface Mining | ||
and Reclamation Division, Railroad Commission of Texas, or the | ||
director's representative. | ||
SECTION 2. Section 134.080, Natural Resources Code, is | ||
amended to read as follows: | ||
Sec. 134.080. APPROVAL [ |
||
[ |
||
revision unless the commission finds that reclamation as required | ||
by this chapter can be accomplished under the revised reclamation | ||
plan. | ||
[ |
||
|
||
|
||
SECTION 3. Subchapter D, Chapter 134, Natural Resources | ||
Code, is amended by adding Section 134.085 to read as follows: | ||
Sec. 134.085. REVIEW PERIODS FOR NEW PERMITS, RENEWALS, AND | ||
REVISIONS. (a) Not later than the seventh day after the date the | ||
commission receives an application for a new permit or for renewal | ||
or a significant revision of a permit, the director shall complete a | ||
review of the application to determine whether the application is | ||
complete. | ||
(b) If the director determines that the application is | ||
complete, the director shall file the application with the | ||
commission's office of general counsel for processing under | ||
commission rules and Chapter 2001, Government Code. | ||
(c) If the director determines that the application is not | ||
complete, the director shall send a written notice to the applicant | ||
that identifies the specific information that the applicant must | ||
provide to the commission. Not later than the seventh day after the | ||
date the commission receives the requested information, the | ||
director shall complete another review of the application to assess | ||
the completeness of the application. | ||
(d) Not later than the 120th day after the date the | ||
commission receives an application described by Subsection (a) that | ||
the director determines is complete, the director shall complete | ||
the technical review of the application and make a recommendation | ||
to approve or deny the application to the commission's office of | ||
general counsel. | ||
(e) If the director determines that the application is | ||
deficient under Subsection (d): | ||
(1) the period required by Subsection (d) for | ||
completing the review of the application is tolled until the date | ||
the commission receives the requested information from the | ||
applicant; and | ||
(2) the director shall send a written notice to the | ||
applicant that notifies the applicant: | ||
(A) that the review period required by Subsection | ||
(d) is being tolled; | ||
(B) of the reason the review period is being | ||
tolled; | ||
(C) of the information the applicant must submit | ||
to the commission before the commission will resume the review of | ||
the application; and | ||
(D) of the number of days remaining that the | ||
commission has to review the application after the commission | ||
receives the requested information from the applicant. | ||
(f) If the applicant submits supplemental information to | ||
the commission that is not in response to a request for information | ||
under Subsection (e), the director may extend the review period | ||
required by Subsection (d) for an additional period of not more than | ||
60 days. The director shall provide written notice to the applicant | ||
that includes the director's decision regarding whether to extend | ||
the review period, the reason for the decision, and the number of | ||
days remaining in the review period. | ||
(g) This subsection and Subsection (h) apply only to an | ||
application for a permit revision that the director determines is | ||
not a significant departure from the approved method or conduct of | ||
mining and reclamation operations. Not later than the 90th day | ||
after the date the commission receives a complete application, the | ||
director shall provide written notice to the applicant that the | ||
permit revision request has been approved or denied. | ||
(h) If the director determines that the application is | ||
deficient: | ||
(1) the review period required by Subsection (g) to | ||
approve or deny the application under this section is tolled until | ||
the date the commission receives the requested information from the | ||
applicant; and | ||
(2) the director shall send a written notice to the | ||
applicant that notifies the applicant: | ||
(A) that the review period required by Subsection | ||
(g) is being tolled; | ||
(B) of the reason the review period is being | ||
tolled; | ||
(C) of the information that the applicant must | ||
submit to the commission before the commission will resume the | ||
review of the revision application; and | ||
(D) of the number of days remaining that the | ||
commission has to review the application after the commission | ||
receives the requested information from the applicant. | ||
SECTION 4. The change in law made by this Act applies only | ||
to a permit to conduct mining operations the application for which | ||
is filed with the Railroad Commission of Texas on or after the | ||
effective date of this Act. A permit the application for which is | ||
filed before the effective date of this Act is subject to the law in | ||
effect on the date the application is filed, and that law is | ||
continued in effect for that purpose. | ||
SECTION 5. This Act takes effect immediately if it receives | ||
a vote of two-thirds of all the members elected to each house, as | ||
provided by Section 39, Article III, Texas Constitution. If this | ||
Act does not receive the vote necessary for immediate effect, this | ||
Act takes effect September 1, 2011. | ||
______________________________ | ______________________________ | |
President of the Senate | Speaker of the House | |
I hereby certify that S.B. No. 1478 passed the Senate on | ||
April 28, 2011, by the following vote: Yeas 31, Nays 0. | ||
______________________________ | ||
Secretary of the Senate | ||
I hereby certify that S.B. No. 1478 passed the House on | ||
May 10, 2011, by the following vote: Yeas 142, Nays 0, two | ||
present not voting. | ||
______________________________ | ||
Chief Clerk of the House | ||
Approved: | ||
______________________________ | ||
Date | ||
______________________________ | ||
Governor |